Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,533
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0283 # 06 Y:2005 | 06 | 2005 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,320 | $236 | Not Implemented |
MS0283 # 07 Y:2005 | 07 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,316 | $2,025 | Not Implemented |
MS0283 # 08 Y:2005 | 08 | 2005 | INSTALL OCCUPANCY SENSORS | $402 | $556 | Not Implemented |
MS0283 # 09 Y:2005 | 09 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $401 | $1,066 | Not Implemented |
SU0221 # 01 Y:2005 | 01 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $20,043 | $0 | Implemented |
SU0221 # 02 Y:2005 | 02 | 2005 | USE SYNTHETIC LUBRICANT | $1,767 | $0 | Implemented |
SU0221 # 03 Y:2005 | 03 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,455 | $0 | Implemented |
SU0221 # 04 Y:2005 | 04 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $320 | $0 | Implemented |
SU0221 # 05 Y:2005 | 05 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $7,835 | $444 | Not Implemented |
SU0221 # 06 Y:2005 | 06 | 2005 | INSTALL TURBULATORS | $1,056 | $271 | Not Implemented |
SU0221 # 07 Y:2005 | 07 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,388 | $2,015 | Implemented |
SU0221 # 08 Y:2005 | 08 | 2005 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,125 | $5,000 | Not Implemented |
SU0221 # 09 Y:2005 | 09 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $129 | $1,155 | Implemented |
SU0221 # 10 Y:2005 | 10 | 2005 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $259 | $721 | Implemented |
SU0221 # 11 Y:2005 | 11 | 2005 | INSTALL OCCUPANCY SENSORS | $96 | $391 | Implemented |
TA0102 # 01 Y:2005 | 01 | 2005 | USE POWER DURING OFF-PEAK PERIODS | $20,445 | $0 | Implemented |
TA0102 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,027 | $110 | Implemented |
TA0102 # 03 Y:2005 | 03 | 2005 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $4,700 | $1,800 | Implemented |
TA0102 # 04 Y:2005 | 04 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,170 | $0 | Not Implemented |
TA0102 # 05 Y:2005 | 05 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $245 | $148 | Not Implemented |
UD0730 # 01 Y:2005 | 01 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $40,357 | $3,600 | Not Implemented |
UD0730 # 02 Y:2005 | 02 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $29,475 | $7,200 | Not Implemented |
UD0730 # 03 Y:2005 | 03 | 2005 | MINIMIZE NON-ESSENTIAL MATERIAL IN HEAT TREATMENT PROCESS | $13,381 | $25,000 | Not Implemented |
UD0730 # 04 Y:2005 | 04 | 2005 | COVER OPEN TANKS | $12,069 | $2,170 | Not Implemented |
UD0730 # 05 Y:2005 | 05 | 2005 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,473 | $12,880 | Implemented |