Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,091
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0351 # 03 Y:1991 | 03 | 1991 | INSTALL SET-BACK TIMERS | $693 | $400 | Implemented |
KU0351 # 04 Y:1991 | 04 | 1991 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $1,047 | $1,600 | Implemented |
KU0351 # 05 Y:1991 | 05 | 1991 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $662 | $0 | Implemented |
KU0352 # 01 Y:1991 | 01 | 1991 | INSTALL SET-BACK TIMERS | $4,777 | $2,460 | Implemented |
KU0352 # 02 Y:1991 | 02 | 1991 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $796 | $360 | Implemented |
KU0352 # 03 Y:1991 | 03 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $409 | $0 | Implemented |
KU0352 # 04 Y:1991 | 04 | 1991 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,963 | $3,800 | Implemented |
KU0352 # 05 Y:1991 | 05 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,658 | $500 | Implemented |
KU0352 # 06 Y:1991 | 06 | 1991 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,322 | $0 | Implemented |
KU0352 # 07 Y:1991 | 07 | 1991 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $735 | $2,200 | Implemented |
KU0352 # 08 Y:1991 | 08 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $344 | $0 | Implemented |
KU0353 # 01 Y:1991 | 01 | 1991 | USE ONLY AMOUNT OF PACKAGING MATERIAL NECESSARY | $26,522 | $0 | Implemented |
KU0353 # 02 Y:1991 | 02 | 1991 | RECOVER AND REUSE COOLING WATER | $603 | $0 | Implemented |
KU0353 # 03 Y:1991 | 03 | 1991 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,291 | $2,400 | Implemented |
KU0353 # 04 Y:1991 | 04 | 1991 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $752 | $120 | Implemented |
KU0353 # 05 Y:1991 | 05 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $386 | $420 | Implemented |
KU0353 # 06 Y:1991 | 06 | 1991 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $315 | $175 | Implemented |
KU0353 # 07 Y:1991 | 07 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $297 | $1,000 | Implemented |
KU0353 # 08 Y:1991 | 08 | 1991 | INSTALL SET-BACK TIMERS | $1,871 | $300 | Implemented |
KU0353 # 09 Y:1991 | 09 | 1991 | REDUCE GLAZED AREAS IN BUILDINGS | $1,259 | $1,105 | Implemented |
RU0123 # 04 Y:1991 | 04 | 1991 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $5,390 | $5,320 | Implemented |
RU0124 # 01 Y:1991 | 01 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,053 | $0 | Implemented |
RU0124 # 02 Y:1991 | 02 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $9,332 | $272 | Implemented |
RU0124 # 03 Y:1991 | 03 | 1991 | IMPROVE LUBRICATION PRACTICES | $2,430 | $800 | Implemented |
RU0124 # 04 Y:1991 | 04 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,576 | $326 | Implemented |