Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,642
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0201 # 01 Y:2016 | 01 | 2016 | BURN WASTE TO PRODUCE STEAM TO DRIVE A STEAM TURBINE GENERATOR SET AND USE STEAM EXHAUST FOR HEAT | $108,895 | $375,000 | Not Implemented |
MZ0201 # 02 Y:2016 | 02 | 2016 | ELIMINATE/REDUCE AN OPERATION | $8,491 | $0 | Not Implemented |
MZ0201 # 03 Y:2016 | 03 | 2016 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $19,426 | $0 | Not Implemented |
MZ0201 # 04 Y:2016 | 04 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,717 | $0 | Not Implemented |
MZ0201 # 05 Y:2016 | 05 | 2016 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $12,192 | $12,000 | Not Implemented |
MZ0201 # 06 Y:2016 | 06 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,397 | $1,500 | Not Implemented |
MZ0201 # 07 Y:2016 | 07 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,703 | $930 | Not Implemented |
MZ0201 # 08 Y:2016 | 08 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $45,907 | $136,500 | Implemented |
MZ0201 # 09 Y:2016 | 09 | 2016 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $6,653 | $0 | Not Implemented |
MZ0202 # 01 Y:2016 | 01 | 2016 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $19,101 | $70,000 | Not Implemented |
MZ0202 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,180 | $27,600 | Not Implemented |
MZ0202 # 03 Y:2016 | 03 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $6,654 | $5,000 | Not Implemented |
MZ0202 # 04 Y:2016 | 04 | 2016 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,839 | $3,225 | Not Implemented |
MZ0202 # 05 Y:2016 | 05 | 2016 | UPGRADE CONTROLS ON COMPRESSORS | $9,678 | $45,000 | Not Implemented |
MZ0202 # 06 Y:2016 | 06 | 2016 | CONDENSE OPERATION INTO ONE BUILDING | $3,585 | $0 | Not Implemented |
MZ0202 # 07 Y:2016 | 07 | 2016 | CONDENSE OPERATION INTO ONE BUILDING | $7,503 | $0 | Not Implemented |
MZ0202 # 08 Y:2016 | 08 | 2016 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,722 | $7,341 | Not Implemented |
MZ0203 # 01 Y:2016 | 01 | 2016 | INSTALL OCCUPANCY SENSORS | $3,747 | $680 | Implemented |
MZ0203 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,707 | $11,425 | Implemented |
MZ0203 # 03 Y:2016 | 03 | 2016 | INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM | $324 | $1,975 | Implemented |
MZ0203 # 04 Y:2016 | 04 | 2016 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $6,109 | $37,500 | Not Implemented |
MZ0196 # 01 Y:2015 | 01 | 2015 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $1,679 | $10,800 | Not Implemented |
MZ0196 # 02 Y:2015 | 02 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,588 | $1,200 | Implemented |
MZ0196 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,414 | $11,400 | Implemented |
MZ0196 # 04 Y:2015 | 04 | 2015 | INSTALL OCCUPANCY SENSORS | $1,428 | $500 | Not Implemented |