Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,969
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0637 # 08 Y:2008 | 08 | 2008 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $18,443 | $16,000 | Not Implemented |
MA0637 # 09 Y:2008 | 09 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,892 | $15,000 | Not Implemented |
MA0637 # 10 Y:2008 | 10 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,680 | $20,000 | Not Implemented |
MA0637 # 11 Y:2008 | 11 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,939 | $10,400 | Not Implemented |
MA0637 # 12 Y:2008 | 12 | 2008 | USE GRAVITY FEEDS WHEREVER POSSIBLE | $455 | $500 | Not Implemented |
MA0636 # 01 Y:2008 | 01 | 2008 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $221,387 | $110,000 | Not Implemented |
MA0636 # 02 Y:2008 | 02 | 2008 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $147,853 | $540,000 | Not Implemented |
MA0636 # 03 Y:2008 | 03 | 2008 | USE EXISTING DAM TO GENERATE ELECTRICITY | $110,112 | $939,500 | Implemented |
MA0636 # 04 Y:2008 | 04 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,946 | $18,000 | Implemented |
MA0636 # 05 Y:2008 | 05 | 2008 | USE STEAM PRESSURE REDUCTION TO GENERATE POWER | $8,663 | $5,000 | Not Implemented |
MA0636 # 06 Y:2008 | 06 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,272 | $0 | Not Implemented |
MA0636 # 07 Y:2008 | 07 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,142 | $20,000 | Not Implemented |
MA0633 # 01 Y:2008 | 01 | 2008 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $76,628 | $85,000 | Not Implemented |
MA0633 # 02 Y:2008 | 02 | 2008 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $8,944 | $25,000 | Not Implemented |
MA0633 # 03 Y:2008 | 03 | 2008 | INSTALL / REPAIR INSULATION ON STEAM LINES | $857 | $300 | Not Implemented |
MA0633 # 04 Y:2008 | 04 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,171 | $0 | Not Implemented |
MA0635 # 01 Y:2008 | 01 | 2008 | USE MINIMUM SAFE OVEN VENTILATION | $17,227 | $51,900 | Implemented |
MA0635 # 02 Y:2008 | 02 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,508 | $40,166 | Not Implemented |
MA0635 # 03 Y:2008 | 03 | 2008 | REDUCE VENTILATION AIR | $21,303 | $8,200 | Implemented |
MA0635 # 04 Y:2008 | 04 | 2008 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $18,922 | $4,000 | Implemented |
MA0635 # 05 Y:2008 | 05 | 2008 | BURN A LESS EXPENSIVE GRADE OF FUEL | $16,990 | $27,590 | Implemented |
MA0635 # 06 Y:2008 | 06 | 2008 | COVER OPEN TANKS | $13,756 | $53,000 | Implemented |
MA0635 # 07 Y:2008 | 07 | 2008 | INSTALL / REPAIR INSULATION ON STEAM LINES | $10,446 | $3,288 | Implemented |
MA0635 # 08 Y:2008 | 08 | 2008 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $4,508 | $12,000 | Not Implemented |
MA0635 # 09 Y:2008 | 09 | 2008 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $3,255 | $5,700 | Not Implemented |