Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,708
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0301 # 03 Y:2002 | 03 | 2002 | INSTALL OCCUPANCY SENSORS | $118 | $399 | Not Implemented |
IA0301 # 04 Y:2002 | 04 | 2002 | USE PHOTOCELL CONTROLS | $386 | $156 | Not Implemented |
IA0301 # 05 Y:2002 | 05 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,699 | $0 | Not Implemented |
IA0301 # 06 Y:2002 | 06 | 2002 | REPAIR AND ELIMINATE STEAM LEAKS | $892 | $340 | Implemented |
IA0301 # 07 Y:2002 | 07 | 2002 | ADJUST BURNERS FOR EFFICIENT OPERATION | $8,453 | $80 | Implemented |
IA0301 # 08 Y:2002 | 08 | 2002 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,523 | $1,465 | Implemented |
IA0301 # 09 Y:2002 | 09 | 2002 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $118,409 | $74,000 | Implemented |
CO0512 # 01 Y:2002 | 01 | 2002 | INSULATE BARE EQUIPMENT | $20,150 | $7,050 | Not Implemented |
CO0512 # 02 Y:2002 | 02 | 2002 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,930 | $2,500 | Implemented |
CO0512 # 03 Y:2002 | 03 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,440 | $12,820 | Not Implemented |
CO0512 # 04 Y:2002 | 04 | 2002 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $5,100 | $3,480 | Not Implemented |
CO0512 # 05 Y:2002 | 05 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,340 | $240 | Implemented |
CO0512 # 06 Y:2002 | 06 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,370 | $3,860 | Not Implemented |
CO0512 # 07 Y:2002 | 07 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $446 | $434 | Implemented |
CO0512 # 08 Y:2002 | 08 | 2002 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $264,970 | $175,000 | n/a |
OR0416 # 01 Y:2002 | 01 | 2002 | UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS | $140,000 | $790,000 | Not Implemented |
OR0416 # 02 Y:2002 | 02 | 2002 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $19,366 | $0 | Not Implemented |
OR0416 # 03 Y:2002 | 03 | 2002 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $13,308 | $0 | Not Implemented |
OR0416 # 04 Y:2002 | 04 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,862 | $1,500 | Not Implemented |
OR0416 # 05 Y:2002 | 05 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $32,840 | $32,942 | Not Implemented |
OR0416 # 06 Y:2002 | 06 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $11,200 | $0 | Not Implemented |
OR0416 # 07 Y:2002 | 07 | 2002 | OPTIMIZE PLANT POWER FACTOR | $15,524 | $38,000 | Not Implemented |
OR0417 # 01 Y:2002 | 01 | 2002 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $26,500 | $0 | Not Implemented |
OR0417 # 02 Y:2002 | 02 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,232 | $0 | Implemented |
OR0417 # 03 Y:2002 | 03 | 2002 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $6,232 | $900 | Implemented |