IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,215

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SU0392 # 08 Y:2015 08 2015 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $251 $654 Implemented
SU0392 # 09 Y:2015 09 2015 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $108 $281 Implemented
SU0392 # 10 Y:2015 10 2015 REDUCE VENTILATION AIR $234 $794 Implemented
SU0392 # 11 Y:2015 11 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,745 $8,154 Implemented
AM0690 # 01 Y:2015 01 2015 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $17,950 $12,830 Not Implemented
AM0690 # 02 Y:2015 02 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $17,320 $2,000 Not Implemented
AM0690 # 03 Y:2015 03 2015 OPTIMIZE PLANT POWER FACTOR $14,550 $31,640 Not Implemented
AM0690 # 04 Y:2015 04 2015 OPTIMIZE PLANT POWER FACTOR $11,210 $21,860 Not Implemented
AM0690 # 05 Y:2015 05 2015 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $8,400 $9,800 Not Implemented
AM0690 # 06 Y:2015 06 2015 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $8,190 $10,960 Not Implemented
AM0690 # 07 Y:2015 07 2015 OPTIMIZE PLANT POWER FACTOR $4,570 $11,330 Not Implemented
AM0690 # 08 Y:2015 08 2015 INSTALL OCCUPANCY SENSORS $4,060 $1,270 Not Implemented
AM0690 # 09 Y:2015 09 2015 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,330 $30 Not Implemented
IP0046 # 01 Y:2015 01 2015 UPGRADE OBSOLETE EQUIPMENT $1,665 $4 Not Implemented
IP0046 # 02 Y:2015 02 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,302 $64 Not Implemented
IP0046 # 03 Y:2015 03 2015 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $122 $117 Not Implemented
IP0046 # 04 Y:2015 04 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,526 $4,032 Not Implemented
IP0046 # 05 Y:2015 05 2015 INSTALL OCCUPANCY SENSORS $348 $512 Not Implemented
IP0046 # 06 Y:2015 06 2015 REPLACE AIR CURTAIN DOORS WITH SOLID DOORS $6,619 $10,141 Not Implemented
NC0554 # 01 Y:2015 01 2015 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $5,085 $12,500 Implemented
NC0554 # 02 Y:2015 02 2015 INSULATE BARE EQUIPMENT $10,751 $8,568 Not Implemented
NC0554 # 03 Y:2015 03 2015 RECOVER WASTE HEAT FROM EQUIPMENT $1,597 $4,400 Implemented
NC0554 # 04 Y:2015 04 2015 RECOVER WASTE HEAT FROM EQUIPMENT $8,465 $12,000 Implemented
NC0554 # 05 Y:2015 05 2015 RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING $3,916 $4,500 Not Implemented
NC0554 # 06 Y:2015 06 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,384 $100 Implemented