Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
144,158
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1056 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $36,442 | $0 | Implemented |
UD1056 # 05 Y:2023 | 05 | 2023 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $17,114 | $3,100 | Implemented |
UD1056 # 06 Y:2023 | 06 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,784 | $0 | Implemented |
UD1056 # 07 Y:2023 | 07 | 2023 | REPAIR OR REPLACE STEAM TRAPS | $7,938 | $800 | Implemented |
UD1056 # 08 Y:2023 | 08 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $23,824 | $0 | Implemented |
UD1056 # 09 Y:2023 | 09 | 2023 | INSTALL OCCUPANCY SENSORS | $7,204 | $1,800 | Implemented |
UD1056 # 10 Y:2023 | 10 | 2023 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,229 | $0 | Not Implemented |
UD1056 # 11 Y:2023 | 11 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $228 | $368 | Implemented |
UD1056 # 12 Y:2023 | 12 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $15,983 | $148,109 | Not Implemented |
MS0414 # 01 Y:2023 | 01 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,690 | $1,580 | Not Implemented |
MS0414 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,129 | $37,628 | Not Implemented |
MS0414 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $45,723 | $532,875 | Not Implemented |
MS0414 # 04 Y:2023 | 04 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $11,747 | $144,100 | Not Implemented |
TR0041 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,679 | $3,857 | Implemented |
TR0041 # 02 Y:2022 | 02 | 2022 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $28,659 | $27,941 | Implemented |
TR0041 # 03 Y:2022 | 03 | 2022 | UPGRADE OBSOLETE EQUIPMENT | $17,496 | $200,000 | Implemented |
SU0531 # 01 Y:2023 | 01 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $6,031 | $0 | n/a |
SU0531 # 02 Y:2023 | 02 | 2023 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,557 | $0 | n/a |
SU0531 # 03 Y:2023 | 03 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,464 | $0 | n/a |
SU0531 # 04 Y:2023 | 04 | 2023 | DISCONNECT BALLASTS | $603 | $0 | n/a |
SU0531 # 05 Y:2023 | 05 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,436 | $70 | n/a |
SU0531 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,000 | $102 | n/a |
SU0531 # 07 Y:2023 | 07 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,355 | $156 | n/a |
SU0531 # 08 Y:2023 | 08 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $32,789 | $29,395 | n/a |
SU0531 # 09 Y:2023 | 09 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $428 | $528 | n/a |