Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,602
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TR0020 # 06 Y:2020 | 06 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $25,280 | $40,101 | Not Implemented |
AM0792 # 01 Y:2019 | 01 | 2019 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $2,250 | $2,000 | Implemented |
AM0792 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,230 | $500 | Implemented |
AM0792 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,122 | $3,340 | Implemented |
AM0792 # 04 Y:2019 | 04 | 2019 | USE PHOTOCELL CONTROLS | $426 | $150 | Implemented |
AM0792 # 05 Y:2019 | 05 | 2019 | USE SYNTHETIC LUBRICANT | $340 | $100 | Implemented |
AM0791 # 01 Y:2019 | 01 | 2019 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $282,870 | $5,000 | Implemented |
AM0791 # 02 Y:2019 | 02 | 2019 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $56,640 | $5,000 | Implemented |
AM0791 # 03 Y:2019 | 03 | 2019 | OPTIMIZE PLANT POWER FACTOR | $40,100 | $66,545 | Implemented |
AM0791 # 04 Y:2019 | 04 | 2019 | INSTALL OCCUPANCY SENSORS | $2,180 | $1,670 | Not Implemented |
AM0791 # 05 Y:2019 | 05 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,725 | $2,590 | Not Implemented |
AM0791 # 06 Y:2019 | 06 | 2019 | PAY UTILITY BILLS ON TIME | $540 | $0 | Implemented |
AM0791 # 07 Y:2019 | 07 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $335 | $8 | Implemented |
AM0790 # 01 Y:2019 | 01 | 2019 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $13,870 | $29,400 | Implemented |
AM0790 # 02 Y:2019 | 02 | 2019 | OPTIMIZE PLANT POWER FACTOR | $4,100 | $5,300 | Implemented |
AM0790 # 03 Y:2019 | 03 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,921 | $12,100 | Implemented |
AM0790 # 04 Y:2019 | 04 | 2019 | USE SYNTHETIC LUBRICANT | $415 | $510 | Implemented |
AM0790 # 05 Y:2019 | 05 | 2019 | USE PHOTOCELL CONTROLS | $235 | $17 | Implemented |
AM0789 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,740 | $46,480 | Implemented |
AM0789 # 02 Y:2019 | 02 | 2019 | OPTIMIZE PLANT POWER FACTOR | $15,300 | $53,500 | Implemented |
AM0789 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,100 | $2,000 | Implemented |
AM0789 # 04 Y:2019 | 04 | 2019 | INSTALL SKYLIGHTS | $4,290 | $7,120 | Not Implemented |
AM0789 # 05 Y:2019 | 05 | 2019 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $3,600 | $0 | Implemented |
AM0789 # 06 Y:2019 | 06 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,900 | $1,620 | Implemented |
TR0019 # 01 Y:2019 | 01 | 2019 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $41,476 | $21,000 | Not Implemented |