Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,615
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
ME0156 # 04 Y:1995 | 04 | 1995 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $750 | $0 | Not Implemented |
ME0155 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,097 | $20,385 | Implemented |
ME0155 # 02 Y:1995 | 02 | 1995 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $12,904 | $20,000 | Implemented |
ME0155 # 03 Y:1995 | 03 | 1995 | CLOSE OFF UNNEEDED STEAM LINES | $1,120 | $200 | Implemented |
ME0155 # 04 Y:1995 | 04 | 1995 | INSTALL / REPAIR INSULATION ON STEAM LINES | $952 | $350 | Implemented |
ME0155 # 05 Y:1995 | 05 | 1995 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $907 | $400 | Implemented |
ME0155 # 06 Y:1995 | 06 | 1995 | USE OPTIMUM THICKNESS INSULATION | $772 | $130 | Implemented |
ME0154 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,883 | $50,267 | Not Implemented |
ME0154 # 02 Y:1995 | 02 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,527 | $1,500 | Not Implemented |
ME0154 # 03 Y:1995 | 03 | 1995 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $5,200 | $400 | Not Implemented |
ME0154 # 04 Y:1995 | 04 | 1995 | PURCHASE EQUIPMENT INSTEAD OF LEASING | $11,057 | $30,000 | Not Implemented |
ME0154 # 05 Y:1995 | 05 | 1995 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,796 | $980 | Not Implemented |
ME0154 # 06 Y:1995 | 06 | 1995 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,537 | $1,175 | Implemented |
ME0154 # 07 Y:1995 | 07 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,118 | $800 | Not Implemented |
ME0154 # 08 Y:1995 | 08 | 1995 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,900 | $400 | Implemented |
ME0154 # 09 Y:1995 | 09 | 1995 | MINIMIZE WATER USAGE | $2,815 | $440 | Implemented |
ME0154 # 10 Y:1995 | 10 | 1995 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $300 | $150 | Not Implemented |
ME0153 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,033 | $32,229 | Implemented |
ME0153 # 02 Y:1995 | 02 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,450 | $750 | Implemented |
ME0153 # 03 Y:1995 | 03 | 1995 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,432 | $0 | Not Implemented |
ME0153 # 04 Y:1995 | 04 | 1995 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $899 | $1,350 | Implemented |
ME0153 # 05 Y:1995 | 05 | 1995 | INSTALL OCCUPANCY SENSORS | $650 | $300 | Not Implemented |
ME0153 # 06 Y:1995 | 06 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $580 | $300 | Implemented |
ME0153 # 07 Y:1995 | 07 | 1995 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $22,220 | $30,000 | Not Implemented |
ME0153 # 08 Y:1995 | 08 | 1995 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $13,800 | $10,000 | Implemented |