IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

5,754

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0813 # 02 Y:2011 02 2011 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $52,531 $65,527 Implemented
OK0813 # 03 Y:2011 03 2011 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $5,048 $6,145 Not Implemented
OK0813 # 04 Y:2011 04 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,656 $11,978 Not Implemented
OK0813 # 05 Y:2011 05 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,469 $7,737 Implemented
OK0813 # 06 Y:2011 06 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,231 $64,515 Implemented
OK0813 # 07 Y:2011 07 2011 OPTIMIZE PLANT POWER FACTOR $19,954 $13,110 Implemented
OK0813 # 08 Y:2011 08 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,672 $990 Implemented
OK0813 # 09 Y:2011 09 2011 INSULATE BARE EQUIPMENT $1,037 $190 Implemented
OK0813 # 10 Y:2011 10 2011 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $19,937 $8,250 Not Implemented
OK0813 # 11 Y:2011 11 2011 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $8,447 $25,472 Implemented
OK0812 # 01 Y:2011 01 2011 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $34,390 $92,072 Implemented
OK0812 # 02 Y:2011 02 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,843 $750 Implemented
OK0812 # 03 Y:2011 03 2011 INSTALL OCCUPANCY SENSORS $11,401 $77,770 Not Implemented
OK0812 # 04 Y:2011 04 2011 INSTALL OCCUPANCY SENSORS $6,323 $26,111 Implemented
OK0812 # 05 Y:2011 05 2011 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR $13,390 $7,255 Not Implemented
OK0812 # 06 Y:2011 06 2011 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS $12,936 $21,477 Not Implemented
OK0812 # 07 Y:2011 07 2011 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,301 $7,605 Not Implemented
OK0812 # 08 Y:2011 08 2011 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $2,925 $14,300 Implemented
OK0812 # 09 Y:2011 09 2011 INSTALL TIMERS AND/OR THERMOSTATS $801 $353 Implemented
OK0812 # 10 Y:2011 10 2011 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,148 $7,130 Not Implemented
OK0811 # 01 Y:2011 01 2011 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $127,513 $58,126 Not Implemented
OK0811 # 02 Y:2011 02 2011 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $17,432 $60,934 Not Implemented
OK0811 # 03 Y:2011 03 2011 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $2,854 $2,600 Implemented
OK0811 # 04 Y:2011 04 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,132 $60,156 Not Implemented
OK0811 # 05 Y:2011 05 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $8,716 $11,429 Not Implemented