Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,105
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0233 # 04 Y:2003 | 04 | 2003 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $12,291 | $36,800 | Implemented |
MS0233 # 05 Y:2003 | 05 | 2003 | INSTALL TIMERS AND/OR THERMOSTATS | $11,372 | $2,900 | Implemented |
MS0233 # 06 Y:2003 | 06 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,999 | $748 | Implemented |
MS0233 # 07 Y:2003 | 07 | 2003 | USE SYNTHETIC LUBRICANT | $3,787 | $1,210 | Implemented |
MS0233 # 08 Y:2003 | 08 | 2003 | INSTALL TIMERS AND/OR THERMOSTATS | $1,622 | $1,535 | Not Implemented |
MS0233 # 09 Y:2003 | 09 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $579 | $968 | Implemented |
UU0052 # 01 Y:2003 | 01 | 2003 | OPTIMIZE PLANT POWER FACTOR | $12,731 | $22,600 | n/a |
UU0052 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,035 | $134 | n/a |
UU0052 # 03 Y:2003 | 03 | 2003 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,186 | $2,810 | n/a |
UU0052 # 04 Y:2003 | 04 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,302 | $1,661 | n/a |
UU0052 # 05 Y:2003 | 05 | 2003 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,027 | $6,000 | n/a |
UU0052 # 06 Y:2003 | 06 | 2003 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,237 | $410 | n/a |
UU0052 # 07 Y:2003 | 07 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $392 | $594 | n/a |
UU0052 # 08 Y:2003 | 08 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,664 | $3,366 | n/a |
UU0052 # 09 Y:2003 | 09 | 2003 | RECOVER AND REUSE WASTE MATERIAL | $50 | $0 | n/a |
WI0450 # 01 Y:2003 | 01 | 2003 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $137,202 | $84,000 | Not Implemented |
WI0450 # 02 Y:2003 | 02 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $64,456 | $144,540 | n/a |
WI0450 # 03 Y:2003 | 03 | 2003 | UPGRADE CONTROLS ON COMPRESSORS | $10,369 | $22,000 | Not Implemented |
WI0450 # 04 Y:2003 | 04 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $9,686 | $5,767 | Not Implemented |
WI0450 # 05 Y:2003 | 05 | 2003 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $5,580 | $12,500 | Not Implemented |
WI0450 # 06 Y:2003 | 06 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,604 | $7,821 | Not Implemented |
WI0450 # 07 Y:2003 | 07 | 2003 | REPLACE CLOTH RAGS WITH PAPER TOWELS | $1,800 | $0 | Not Implemented |
UF0330 # 01 Y:2003 | 01 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,935 | $0 | Not Implemented |
UF0330 # 02 Y:2003 | 02 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,321 | $0 | Not Implemented |
UF0330 # 03 Y:2003 | 03 | 2003 | DO NOT USE COMPRESSED AIR FOR PERSONAL COOLING | $1,174 | $0 | Implemented |