Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,602
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0772 # 06 Y:2019 | 06 | 2019 | PAY UTILITY BILLS ON TIME | $3,642 | $0 | Implemented |
AM0772 # 07 Y:2019 | 07 | 2019 | INSTALL OCCUPANCY SENSORS | $365 | $770 | Implemented |
AM0772 # 08 Y:2019 | 08 | 2019 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $650 | $900 | Implemented |
AM0772 # 09 Y:2019 | 09 | 2019 | USE SYNTHETIC LUBRICANT | $387 | $160 | Not Implemented |
AM0772 # 01 Y:2019 | 01 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $18,306 | $1,100 | Implemented |
AM0772 # 02 Y:2019 | 02 | 2019 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $27,900 | $10,000 | Implemented |
AM0771 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,590 | $8,175 | Implemented |
AM0771 # 02 Y:2019 | 02 | 2019 | REPLACE BOILER | $8,200 | $42,760 | Implemented |
AM0771 # 03 Y:2019 | 03 | 2019 | OPTIMIZE PLANT POWER FACTOR | $6,400 | $12,960 | Implemented |
AM0771 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,500 | $1,340 | Implemented |
AM0771 # 05 Y:2019 | 05 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $950 | $0 | Not Implemented |
AM0771 # 06 Y:2019 | 06 | 2019 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $300 | $26 | Implemented |
AM0771 # 07 Y:2019 | 07 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $240 | $350 | Not Implemented |
AM0770 # 01 Y:2019 | 01 | 2019 | OPTIMIZE PLANT POWER FACTOR | $28,900 | $38,900 | Not Implemented |
AM0770 # 02 Y:2019 | 02 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $16,150 | $2,050 | Implemented |
AM0770 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,260 | $27,700 | Implemented |
AM0770 # 04 Y:2019 | 04 | 2019 | OPTIMIZE PLANT POWER FACTOR | $8,810 | $11,400 | Not Implemented |
AM0770 # 05 Y:2019 | 05 | 2019 | OPTIMIZE PLANT POWER FACTOR | $5,940 | $9,940 | Not Implemented |
AM0770 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,700 | $675 | Implemented |
AM0770 # 07 Y:2019 | 07 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,840 | $500 | Implemented |
AM0770 # 08 Y:2019 | 08 | 2019 | USE SYNTHETIC LUBRICANT | $794 | $0 | Not Implemented |
AM0770 # 09 Y:2019 | 09 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,010 | $90 | Not Implemented |
AM0770 # 10 Y:2019 | 10 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $300 | $0 | Not Implemented |
AM0770 # 11 Y:2019 | 11 | 2019 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $175 | $0 | Not Implemented |
AM0769 # 01 Y:2019 | 01 | 2019 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $32,530 | $3,000 | Not Implemented |