Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,573
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IP0050 # 07 Y:2015 | 07 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,348 | $5,370 | Implemented |
IP0050 # 08 Y:2015 | 08 | 2015 | OPTIMIZE PLANT POWER FACTOR | $10,314 | $19,140 | Not Implemented |
IP0050 # 09 Y:2015 | 09 | 2015 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $5,085 | $21,918 | Not Implemented |
IP0049 # 01 Y:2015 | 01 | 2015 | PAY BILLS ON TIME TO AVOID LATE FEES | $4,118 | $0 | Implemented |
IP0049 # 02 Y:2015 | 02 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,197 | $8 | Implemented |
IP0049 # 03 Y:2015 | 03 | 2015 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $6,918 | $400 | Not Implemented |
IP0049 # 04 Y:2015 | 04 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,009 | $70 | Implemented |
IP0049 # 05 Y:2015 | 05 | 2015 | INSTALL OCCUPANCY SENSORS | $1,359 | $770 | Not Implemented |
IP0049 # 06 Y:2015 | 06 | 2015 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $5,511 | $4,400 | Not Implemented |
IP0049 # 07 Y:2015 | 07 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $223 | $283 | Not Implemented |
IP0049 # 08 Y:2015 | 08 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $7,789 | $10,000 | Not Implemented |
IP0049 # 09 Y:2015 | 09 | 2015 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $4,057 | $6,011 | Not Implemented |
IP0049 # 10 Y:2015 | 10 | 2015 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $5,682 | $15,286 | Not Implemented |
IP0049 # 11 Y:2015 | 11 | 2015 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $3,976 | $21,474 | Implemented |
IP0048 # 01 Y:2015 | 01 | 2015 | COMBINE UTILITY METERS | $27,805 | $21 | Not Implemented |
IP0048 # 02 Y:2015 | 02 | 2015 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $16,379 | $5 | Implemented |
IP0048 # 03 Y:2015 | 03 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,718 | $5 | Implemented |
IP0048 # 04 Y:2015 | 04 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $902 | $45 | Implemented |
IP0048 # 05 Y:2015 | 05 | 2015 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,880 | $430 | Implemented |
IP0048 # 06 Y:2015 | 06 | 2015 | AIR CONDITION ONLY SPACE NECESSARY | $394 | $193 | Not Implemented |
IP0048 # 07 Y:2015 | 07 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $8,854 | $4,500 | Not Implemented |
IP0048 # 08 Y:2015 | 08 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $15,491 | $9,000 | Not Implemented |
IP0048 # 09 Y:2015 | 09 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,176 | $8,753 | Implemented |
IP0048 # 10 Y:2015 | 10 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $116 | $413 | Implemented |
IP0047 # 01 Y:2015 | 01 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,458 | $163 | Implemented |