Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,718
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CM1004 # 04 Y:2022 | 04 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,250 | $11,350 | Not Implemented |
CM1004 # 05 Y:2022 | 05 | 2022 | MAKE ICE DURING OFF PEAK HOURS FOR COOLING | $10,340 | $57,600 | Implemented |
CM1004 # 06 Y:2022 | 06 | 2022 | USE BATTERY STORAGE FOR DEMAND CONTROL | $36,190 | $195,000 | Not Implemented |
CM1004 # 07 Y:2022 | 07 | 2022 | APPLY FOR INVESTMENT INCENTIVES | $17,220 | $8,000 | Not Implemented |
DL0208 # 01 Y:2022 | 01 | 2022 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $25,361 | $3,000 | Not Implemented |
DL0208 # 02 Y:2022 | 02 | 2022 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $8,504 | $0 | Not Implemented |
DL0208 # 03 Y:2022 | 03 | 2022 | REDUCE VENTILATION AIR | $4,894 | $0 | Not Implemented |
DL0208 # 04 Y:2022 | 04 | 2022 | TURN OFF EQUIPMENT WHEN NOT IN USE | $583 | $0 | Implemented |
DL0208 # 05 Y:2022 | 05 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $3,567 | $71 | Implemented |
DL0208 # 06 Y:2022 | 06 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $627 | $96 | Not Implemented |
DL0208 # 07 Y:2022 | 07 | 2022 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $23,194 | $11,933 | Implemented |
DL0208 # 08 Y:2022 | 08 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,331 | $2,230 | Implemented |
DL0208 # 09 Y:2022 | 09 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,770 | $33,570 | Implemented |
DL0208 # 10 Y:2022 | 10 | 2022 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $11,982 | $55,000 | Implemented |
DL0208 # 11 Y:2022 | 11 | 2022 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,359 | $7,840 | Not Implemented |
DL0208 # 12 Y:2022 | 12 | 2022 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $436 | $2,500 | Implemented |
IC0264 # 01 Y:2022 | 01 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,084 | $2,113 | Not Implemented |
IC0264 # 02 Y:2022 | 02 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,944 | $4,150 | Implemented |
IC0264 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,361 | $10,377 | Implemented |
IC0264 # 04 Y:2022 | 04 | 2022 | UPGRADE CONTROLS ON COMPRESSORS | $2,600 | $15,017 | Not Implemented |
IC0264 # 05 Y:2022 | 05 | 2022 | OPTIMIZE PLANT POWER FACTOR | $3,552 | $15,893 | Not Implemented |
IC0264 # 06 Y:2022 | 06 | 2022 | REDUCE VENTILATION AIR | $1,650 | $6,000 | Implemented |
IP0160 # 01 Y:2022 | 01 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $13,174 | $0 | Implemented |
IP0160 # 02 Y:2022 | 02 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,950 | $10 | Implemented |
IP0160 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,154 | $1,596 | Implemented |