Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,871
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0674 # 02 Y:2000 | 02 | 2000 | INSTALL EQUIPMENT TO MOVE PRODUCT | $249,860 | $667,440 | Not Implemented |
TN0674 # 03 Y:2000 | 03 | 2000 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $42,930 | $25,500 | Not Implemented |
TN0674 # 04 Y:2000 | 04 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,490 | $750 | Implemented |
TN0674 # 05 Y:2000 | 05 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,380 | $500 | Implemented |
UL0230 # 01 Y:1999 | 01 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,394 | $40 | Implemented |
UL0230 # 02 Y:1999 | 02 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,353 | $500 | Implemented |
UL0230 # 03 Y:1999 | 03 | 1999 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $2,860 | $0 | Not Implemented |
UL0230 # 04 Y:1999 | 04 | 1999 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $1,447 | $0 | Not Implemented |
UL0230 # 05 Y:1999 | 05 | 1999 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $297,462 | $167,000 | Not Implemented |
UL0230 # 06 Y:1999 | 06 | 1999 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $83,800 | $80,000 | Implemented |
UL0230 # 07 Y:1999 | 07 | 1999 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $1,500 | $0 | Implemented |
UL0230 # 08 Y:1999 | 08 | 1999 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $2,893 | $2,120 | Implemented |
UL0230 # 09 Y:1999 | 09 | 1999 | INSTALL SHELVES / RACKS TO UTILIZE UNUSED SPACE | $1,308 | $2,270 | Not Implemented |
UL0233 # 01 Y:1999 | 01 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,210 | $50 | Implemented |
UL0233 # 02 Y:1999 | 02 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,678 | $261 | Not Implemented |
UL0233 # 03 Y:1999 | 03 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $594 | $0 | Not Implemented |
UL0233 # 04 Y:1999 | 04 | 1999 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $5,027 | $4,475 | Implemented |
UL0233 # 05 Y:1999 | 05 | 1999 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $7,011 | $9,500 | Implemented |
UL0233 # 06 Y:1999 | 06 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $10,120 | $0 | Not Implemented |
UL0237 # 01 Y:1999 | 01 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,611 | $100 | Not Implemented |
UL0237 # 02 Y:1999 | 02 | 1999 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $11,512 | $0 | Implemented |
UL0237 # 03 Y:1999 | 03 | 1999 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $5,309 | $0 | Not Implemented |
UL0234 # 01 Y:1999 | 01 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,233 | $20 | Not Implemented |
UL0234 # 02 Y:1999 | 02 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $480 | $131 | Not Implemented |
UL0234 # 03 Y:1999 | 03 | 1999 | INSTALL REDUNDANT EQUIPMENT TO AVOID LOSSES CAUSED BY EQUIPMENT FAILURE AND ROUTINE MAINTENANCE | $11,305 | $800 | Not Implemented |