Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,644
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0345 # 05 Y:2012 | 05 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $21,763 | $3,800 | Implemented |
LE0345 # 06 Y:2012 | 06 | 2012 | INSTALL TIMERS AND/OR THERMOSTATS | $6,352 | $575 | Not Implemented |
LE0345 # 07 Y:2012 | 07 | 2012 | REPLACE BOILER | $226,873 | $560,000 | Implemented |
LE0345 # 08 Y:2012 | 08 | 2012 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $2,858 | $12,810 | Not Implemented |
LE0345 # 09 Y:2012 | 09 | 2012 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $3,306 | $3,800 | Not Implemented |
LE0345 # 10 Y:2012 | 10 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,720 | $7,500 | Not Implemented |
LE0345 # 11 Y:2012 | 11 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $53,742 | $3,200 | Implemented |
LE0340 # 01 Y:2012 | 01 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,181 | $8,250 | Not Implemented |
LE0340 # 02 Y:2012 | 02 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $32,208 | $54,225 | Not Implemented |
LE0340 # 03 Y:2012 | 03 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $953 | $1,000 | Not Implemented |
LE0340 # 04 Y:2012 | 04 | 2012 | INSTALL TIMERS AND/OR THERMOSTATS | $26,676 | $0 | Not Implemented |
LE0340 # 05 Y:2012 | 05 | 2012 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $5,033 | $5,527 | Not Implemented |
LE0340 # 06 Y:2012 | 06 | 2012 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $10,053 | $13,598 | Not Implemented |
LE0340 # 07 Y:2012 | 07 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,391 | $1,900 | Not Implemented |
LE0340 # 08 Y:2012 | 08 | 2012 | INSTALL TIMERS AND/OR THERMOSTATS | $16,632 | $3,000 | Not Implemented |
LE0340 # 09 Y:2012 | 09 | 2012 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,535 | $21,000 | Not Implemented |
LE0340 # 10 Y:2012 | 10 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,096 | $12,800 | Not Implemented |
LE0340 # 11 Y:2012 | 11 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $586 | $800 | Not Implemented |
LE0340 # 12 Y:2012 | 12 | 2012 | INSTALL OCCUPANCY SENSORS | $16,429 | $30,000 | Not Implemented |
LE0340 # 13 Y:2012 | 13 | 2012 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $9,090 | $0 | Not Implemented |
LE0340 # 14 Y:2012 | 14 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $262 | $520 | Not Implemented |
LE0340 # 15 Y:2012 | 15 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,205 | $10,010 | Not Implemented |
WV0450 # 01 Y:2012 | 01 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $173,557 | $1,000 | Implemented |
WV0450 # 02 Y:2012 | 02 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO GENERATE STEAM | $141,590 | $210,000 | Not Implemented |
WV0450 # 03 Y:2012 | 03 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $130,899 | $157,320 | Implemented |