Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,111
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UW2408 # 03 Y:2024 | 03 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,014 | $0 | n/a |
UW2408 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $32,306 | $2,080 | n/a |
UW2408 # 05 Y:2024 | 05 | 2024 | OPTIMIZE PLANT POWER FACTOR | $45,697 | $89,919 | n/a |
UW2408 # 06 Y:2024 | 06 | 2024 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $35,732 | $2,619 | n/a |
UW2408 # 07 Y:2024 | 07 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $34,834 | $133,560 | n/a |
UW2408 # 08 Y:2024 | 08 | 2024 | INSULATE FEEDWATER TANK | $2,901 | $290 | n/a |
UW2408 # 09 Y:2024 | 09 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $61,411 | $421,830 | n/a |
UW2408 # 10 Y:2024 | 10 | 2024 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $145,176 | $144,799 | n/a |
WV0664 # 01 Y:2024 | 01 | 2024 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,899 | $1,019 | n/a |
WV0664 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,056 | $426 | n/a |
WV0664 # 03 Y:2024 | 03 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $2,777 | $3,541 | n/a |
WV0664 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,469 | $12,134 | n/a |
WV0664 # 05 Y:2024 | 05 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $911 | $1,030 | n/a |
WV0664 # 06 Y:2024 | 06 | 2024 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $792 | $1,500 | n/a |
WV0664 # 07 Y:2024 | 07 | 2024 | DEVELOP A REPAIR/REPLACE POLICY | $535 | $1,139 | n/a |
WV0664 # 08 Y:2024 | 08 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $391 | $222 | n/a |
WV0664 # 09 Y:2024 | 09 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $382 | $328 | n/a |
WV0664 # 10 Y:2024 | 10 | 2024 | INSULATE BARE EQUIPMENT | $121 | $293 | n/a |
LE0570 # 01 Y:2024 | 01 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $9,292 | $0 | n/a |
LE0570 # 02 Y:2024 | 02 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $33,515 | $15,000 | n/a |
LE0570 # 03 Y:2024 | 03 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $55,246 | $42,000 | n/a |
LE0570 # 04 Y:2024 | 04 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $25,168 | $26,500 | n/a |
LE0570 # 05 Y:2024 | 05 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,252 | $5,000 | n/a |
LE0570 # 06 Y:2024 | 06 | 2024 | INSTALL BACK-UP EQUIPMENT | $46,731 | $90,000 | n/a |
LS2412 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,703 | $150 | n/a |