Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,302
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0407 # 02 Y:2008 | 02 | 2008 | AIR CONDITION ONLY SPACE NECESSARY | $4,807 | $0 | Not Implemented |
SD0407 # 03 Y:2008 | 03 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,196 | $13,699 | Implemented |
SD0407 # 04 Y:2008 | 04 | 2008 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,008 | $7,140 | Implemented |
SD0407 # 05 Y:2008 | 05 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,341 | $1,374 | Implemented |
SD0407 # 06 Y:2008 | 06 | 2008 | INSTALL SKYLIGHTS | $990 | $2,940 | Not Implemented |
LE0273 # 01 Y:2008 | 01 | 2008 | USE SOLAR HEAT TO MAKE ELECTRICTY | $40,528 | $972,000 | Not Implemented |
LE0273 # 02 Y:2008 | 02 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $14,519 | $1,440 | Implemented |
LE0273 # 03 Y:2008 | 03 | 2008 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $11,082 | $1,560 | Not Implemented |
LE0273 # 04 Y:2008 | 04 | 2008 | USE SOLAR HEAT TO HEAT WATER | $10,101 | $2,730 | Not Implemented |
LE0273 # 05 Y:2008 | 05 | 2008 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $9,907 | $214 | Not Implemented |
LE0273 # 06 Y:2008 | 06 | 2008 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $8,118 | $6,000 | Not Implemented |
LE0273 # 07 Y:2008 | 07 | 2008 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $4,895 | $7,800 | Implemented |
LE0273 # 08 Y:2008 | 08 | 2008 | SHIFT FROM DAYTIME TO NIGHTTIME OPERATION | $4,177 | $3,120 | Not Implemented |
LE0273 # 09 Y:2008 | 09 | 2008 | INSTALL OCCUPANCY SENSORS | $381 | $180 | Not Implemented |
LE0273 # 10 Y:2008 | 10 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,813 | $42,521 | Implemented |
LL0293 # 01 Y:2008 | 01 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $37,156 | $56,346 | Not Implemented |
LL0293 # 02 Y:2008 | 02 | 2008 | INSULATE BARE EQUIPMENT | $3,531 | $655 | Implemented |
LL0293 # 03 Y:2008 | 03 | 2008 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,733 | $60 | Implemented |
LL0293 # 04 Y:2008 | 04 | 2008 | USE PHOTOCELL CONTROLS | $1,073 | $60 | Implemented |
LL0293 # 05 Y:2008 | 05 | 2008 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $889 | $45 | Implemented |
LL0293 # 06 Y:2008 | 06 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $819 | $360 | Implemented |
LL0293 # 07 Y:2008 | 07 | 2008 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $436 | $501 | Not Implemented |
NC0376 # 07 Y:2008 | 07 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $400 | $100 | Implemented |
NC0376 # 08 Y:2008 | 08 | 2008 | DEVELOP A REPAIR/REPLACE POLICY | $4,903 | $7,820 | Implemented |
NC0376 # 09 Y:2008 | 09 | 2008 | USE PHOTOCELL CONTROLS | $2,567 | $1,900 | Implemented |