Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,002
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0340 # 13 Y:2012 | 13 | 2012 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $9,090 | $0 | Not Implemented |
LE0340 # 14 Y:2012 | 14 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $262 | $520 | Not Implemented |
LE0340 # 15 Y:2012 | 15 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,205 | $10,010 | Not Implemented |
SU0323 # 01 Y:2012 | 01 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $387 | $0 | Not Implemented |
SU0323 # 02 Y:2012 | 02 | 2012 | PAY BILLS ON TIME TO AVOID LATE FEES | $131 | $0 | Implemented |
SU0323 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $533 | $197 | Not Implemented |
SU0323 # 04 Y:2012 | 04 | 2012 | ELIMINATE/REDUCE AN OPERATION | $1,819 | $1,200 | Not Implemented |
SU0323 # 05 Y:2012 | 05 | 2012 | INSTALL OCCUPANCY SENSORS | $142 | $218 | Not Implemented |
SU0323 # 06 Y:2012 | 06 | 2012 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $222 | $570 | Not Implemented |
SU0323 # 07 Y:2012 | 07 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $430 | $1,454 | Not Implemented |
SU0323 # 08 Y:2012 | 08 | 2012 | UPGRADE OBSOLETE EQUIPMENT | $103 | $440 | Not Implemented |
SU0323 # 09 Y:2012 | 09 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,340 | $37,030 | Not Implemented |
OR0584 # 01 Y:2012 | 01 | 2012 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $6,320 | $0 | Not Implemented |
OR0584 # 02 Y:2012 | 02 | 2012 | INCREASE AMOUNT OF CONDENSATE RETURNED | $26,558 | $19,925 | Not Implemented |
OR0584 # 03 Y:2012 | 03 | 2012 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $16,839 | $29,000 | Not Implemented |
OR0584 # 04 Y:2012 | 04 | 2012 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $12,631 | $27,000 | Not Implemented |
OR0584 # 05 Y:2012 | 05 | 2012 | MINIMIZE WATER USAGE | $4,574 | $7,000 | Not Implemented |
OR0584 # 06 Y:2012 | 06 | 2012 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $7,796 | $19,701 | Not Implemented |
OR0584 # 07 Y:2012 | 07 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $54,152 | $251,677 | Not Implemented |
UD0858 # 01 Y:2012 | 01 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,297 | $12,425 | Not Implemented |
UD0858 # 02 Y:2012 | 02 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,138 | $3,850 | Not Implemented |
UD0858 # 03 Y:2012 | 03 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,006 | $500 | Implemented |
UD0858 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,010 | $1,000 | Implemented |
UD0858 # 05 Y:2012 | 05 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $399 | $300 | Not Implemented |
UD0858 # 06 Y:2012 | 06 | 2012 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $409 | $360 | Not Implemented |