Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,230
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0451 # 04 Y:2011 | 04 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,153 | $1,277 | Implemented |
UF0451 # 05 Y:2011 | 05 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,440 | $3,310 | Implemented |
UF0451 # 06 Y:2011 | 06 | 2011 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $498 | $0 | Implemented |
UF0451 # 07 Y:2011 | 07 | 2011 | ISOLATE STEAM LINES TO AVOID HEATING AIR CONDITIONED AREAS | $1,379 | $1,140 | Not Implemented |
UF0451 # 08 Y:2011 | 08 | 2011 | USE OPTIMUM THICKNESS INSULATION | $1,327 | $1,865 | Not Implemented |
LL0361 # 01 Y:2011 | 01 | 2011 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,242 | $540 | Not Implemented |
LL0361 # 02 Y:2011 | 02 | 2011 | USE PHOTOCELL CONTROLS | $1,052 | $120 | Not Implemented |
LL0361 # 03 Y:2011 | 03 | 2011 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $868 | $625 | Not Implemented |
LL0361 # 04 Y:2011 | 04 | 2011 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $561 | $90 | Not Implemented |
LL0361 # 05 Y:2011 | 05 | 2011 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $326 | $368 | Not Implemented |
LL0361 # 06 Y:2011 | 06 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $306 | $175 | Not Implemented |
LL0361 # 07 Y:2011 | 07 | 2011 | INSTALL OCCUPANCY SENSORS | $209 | $900 | Not Implemented |
LL0361 # 08 Y:2011 | 08 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $165 | $75 | Not Implemented |
LL0361 # 09 Y:2011 | 09 | 2011 | INSULATE BARE EQUIPMENT | $85 | $345 | Not Implemented |
UM0397 # 01 Y:2011 | 01 | 2011 | UPGRADE CONTROLS ON COMPRESSORS | $5,033 | $200 | Implemented |
UM0397 # 02 Y:2011 | 02 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $13,335 | $30,200 | Not Implemented |
UM0397 # 03 Y:2011 | 03 | 2011 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $239 | $10 | Implemented |
UM0396 # 01 Y:2011 | 01 | 2011 | UPGRADE CONTROLS ON COMPRESSORS | $3,985 | $2,500 | Not Implemented |
MA0682 # 01 Y:2011 | 01 | 2011 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $29,366 | $91,950 | Not Implemented |
MA0682 # 02 Y:2011 | 02 | 2011 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $25,038 | $57,600 | Not Implemented |
MA0682 # 03 Y:2011 | 03 | 2011 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $11,594 | $0 | Implemented |
MA0682 # 04 Y:2011 | 04 | 2011 | USE DIRECT AIR SUPPLY TO EXHAUST HOODS | $10,708 | $29,760 | Implemented |
MA0682 # 05 Y:2011 | 05 | 2011 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,468 | $7,325 | Implemented |
LL0362 # 01 Y:2011 | 01 | 2011 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $18,083 | $810 | Implemented |
LL0362 # 02 Y:2011 | 02 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,629 | $61,377 | Implemented |