Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
273
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0027 # 01 Y:1982 | 01 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $792 | $108 | Not Implemented |
OK0027 # 02 Y:1982 | 02 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $46 | $42 | Not Implemented |
OK0027 # 03 Y:1982 | 03 | 1982 | RECOVER WASTE HEAT FROM EQUIPMENT | $46 | $250 | Not Implemented |
OK0021 # 01 Y:1982 | 01 | 1982 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $417 | $225 | Not Implemented |
OK0021 # 02 Y:1982 | 02 | 1982 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,873 | $1,425 | Not Implemented |
OK0021 # 03 Y:1982 | 03 | 1982 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $3,426 | $24,000 | Not Implemented |
OK0021 # 04 Y:1982 | 04 | 1982 | TURN OFF EQUIPMENT WHEN NOT IN USE | $12,842 | $0 | Not Implemented |
OK0021 # 05 Y:1982 | 05 | 1982 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $6,552 | $6,300 | Not Implemented |
OK0021 # 06 Y:1982 | 06 | 1982 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $3,950 | $1,500 | Not Implemented |
OK0021 # 07 Y:1982 | 07 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $266 | $4,572 | Implemented |
OK0021 # 09 Y:1982 | 09 | 1982 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,184 | $8,662 | Not Implemented |
OK0022 # 01 Y:1982 | 01 | 1982 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,321 | $24,185 | Not Implemented |
OK0022 # 02 Y:1982 | 02 | 1982 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $4,332 | $15,000 | Not Implemented |
OK0022 # 03 Y:1982 | 03 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,256 | $13,760 | Not Implemented |
OK0022 # 04 Y:1982 | 04 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,141 | $6,006 | Not Implemented |
OK0022 # 05 Y:1982 | 05 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $156 | $78 | Not Implemented |
OK0022 # 06 Y:1982 | 06 | 1982 | INSTALL TIMERS AND/OR THERMOSTATS | $150 | $75 | Not Implemented |
OK0024 # 01 Y:1982 | 01 | 1982 | LOWER CEILING TO REDUCE CONDITIONED SPACE | $3,189 | $16,389 | Not Implemented |
OK0024 # 02 Y:1982 | 02 | 1982 | INSTALL STORM WINDOWS AND DOORS | $300 | $566 | Not Implemented |
OK0024 # 03 Y:1982 | 03 | 1982 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $1,502 | $3,500 | Not Implemented |
OK0024 # 04 Y:1982 | 04 | 1982 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $85 | $80 | Not Implemented |
OK0024 # 05 Y:1982 | 05 | 1982 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,135 | $0 | Implemented |
OK0024 # 06 Y:1982 | 06 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $386 | $90 | Not Implemented |
OK0029 # 01 Y:1982 | 01 | 1982 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $6,489 | $0 | Not Implemented |
OK0029 # 02 Y:1982 | 02 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,887 | $18,833 | Not Implemented |