Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
467
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0195 # 06 Y:2000 | 06 | 2000 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $124,556 | $60,000 | Not Implemented |
SF0195 # 07 Y:2000 | 07 | 2000 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $3,147 | $10,300 | Not Implemented |
SF0195 # 08 Y:2000 | 08 | 2000 | $27,873 | $2,000 | Not Implemented | |
NV0155 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $836 | $462 | Not Implemented |
NV0155 # 02 Y:2000 | 02 | 2000 | INSTALL SKYLIGHTS | $4,525 | $8,000 | Implemented |
NV0155 # 03 Y:2000 | 03 | 2000 | TURN OFF EQUIPMENT WHEN NOT IN USE | $782 | $300 | Not Implemented |
NV0155 # 04 Y:2000 | 04 | 2000 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $3,780 | $1,992 | Not Implemented |
NV0155 # 05 Y:2000 | 05 | 2000 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $950 | $1,524 | Not Implemented |
NV0155 # 06 Y:2000 | 06 | 2000 | $13,104 | $7,980 | Not Implemented | |
SD0254 # 01 Y:2000 | 01 | 2000 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $22,489 | $70,000 | Not Implemented |
SD0254 # 02 Y:2000 | 02 | 2000 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $5,944 | $720 | Implemented |
SD0254 # 03 Y:2000 | 03 | 2000 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,974 | $0 | Implemented |
SD0254 # 04 Y:2000 | 04 | 2000 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,675 | $0 | Implemented |
SD0254 # 05 Y:2000 | 05 | 2000 | RECYCLE CASTING SAND | $90,000 | $120,000 | Not Implemented |
SD0254 # 06 Y:2000 | 06 | 2000 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $1,700 | $5,400 | Implemented |
SD0254 # 07 Y:2000 | 07 | 2000 | $10,600 | $23,000 | Not Implemented | |
SD0254 # 08 Y:2000 | 08 | 2000 | $1,992 | $0 | Implemented | |
SF0194 # 01 Y:2000 | 01 | 2000 | ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF | $25,387 | $11,668 | Not Implemented |
SF0194 # 02 Y:2000 | 02 | 2000 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $5,898 | $3,720 | Implemented |
SF0194 # 03 Y:2000 | 03 | 2000 | COVER OPEN TANKS | $550 | $746 | Implemented |
SF0194 # 04 Y:2000 | 04 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $29,331 | $57,900 | Implemented |
SF0194 # 05 Y:2000 | 05 | 2000 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $1,052 | $0 | Implemented |
NV0153 # 01 Y:2000 | 01 | 2000 | IMPROVE COMBUSTION CONTROL CAPABILITY | $3,058 | $5,650 | Not Implemented |
NV0153 # 02 Y:2000 | 02 | 2000 | OPTIMIZE PLANT POWER FACTOR | $12,568 | $9,490 | Implemented |
NV0153 # 03 Y:2000 | 03 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $676 | $200 | Implemented |