IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

418

matching recommendations
Reset
NAICS 331 Primary Metal Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LM0085 # 06 Y:2004 06 2004 $26,300 $4,450 Implemented
LM0085 # 09 Y:2004 09 2004 $3,360 $1,850 Implemented
LM0085 # 01 Y:2004 01 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,324 $205 Implemented
LM0085 # 02 Y:2004 02 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $167 $0 Implemented
LM0085 # 04 Y:2004 04 2004 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING $1,335 $741 Not Implemented
LM0085 # 05 Y:2004 05 2004 ADJUST BURNERS FOR EFFICIENT OPERATION $5,902 $600 Implemented
LM0085 # 03 Y:2004 03 2004 CLEAN FOULING FROM WATER LINES REGULARLY $2,852 $180 Implemented
LM0085 # 10 Y:2004 10 2004 $54,080 $3,320 Implemented
LM0085 # 07 Y:2004 07 2004 $9,060 $1,500 Implemented
LM0085 # 08 Y:2004 08 2004 $18,000 $2,450 Implemented
NC0303 # 05 Y:2004 05 2004 REDESIGN PROCESS $73,700 $35,000 Not Implemented
NC0303 # 02 Y:2004 02 2004 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $20,788 $0 Not Implemented
NC0303 # 04 Y:2004 04 2004 REPLACE THE CHLORINATION STAGE WITH AN OXYGEN OR OZONE STAGE $11,844 $18,280 Not Implemented
NC0303 # 03 Y:2004 03 2004 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $18,426 $18,825 Not Implemented
NC0303 # 01 Y:2004 01 2004 $34,730 $120,000 Not Implemented
NC0303 # 06 Y:2004 06 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,224 $100 Implemented
NC0303 # 07 Y:2004 07 2004 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,085 $1,385 Not Implemented
LE0200 # 07 Y:2004 07 2004 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,132 $400 Implemented
LE0200 # 04 Y:2004 04 2004 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $1,878 $4,000 Implemented
LE0200 # 02 Y:2004 02 2004 AIR CONDITION ONLY SPACE NECESSARY $9,386 $360 Not Implemented
LE0200 # 03 Y:2004 03 2004 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR $3,305 $800 Implemented
LE0200 # 08 Y:2004 08 2004 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $904 $500 Implemented
LE0200 # 01 Y:2004 01 2004 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $18,210 $3,000 Implemented
LE0200 # 06 Y:2004 06 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,198 $0 Implemented
LE0200 # 05 Y:2004 05 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,266 $750 Implemented