Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,724
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LT8363 # 04 Y:2022 | 04 | 2022 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $14,468 | $15,975 | n/a |
LT8363 # 06 Y:2022 | 06 | 2022 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $23,817 | $51,385 | n/a |
LT8363 # 05 Y:2022 | 05 | 2022 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $22,308 | $32,500 | n/a |
LT8363 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,542 | $2,945 | n/a |
LT8363 # 02 Y:2022 | 02 | 2022 | CHANGE OPERATING CONDITIONS | $46,622 | $0 | n/a |
LT8363 # 01 Y:2022 | 01 | 2022 | OPTIMIZE PLANT POWER FACTOR | $5,980 | $10,022 | n/a |
LT8363 # 07 Y:2022 | 07 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,254 | $0 | n/a |
OK1043 # 03 Y:2021 | 03 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $8,309 | $35,400 | Implemented |
OK1043 # 02 Y:2021 | 02 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $331 | $1,650 | Implemented |
OK1043 # 01 Y:2021 | 01 | 2021 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $2,091 | $8,000 | Implemented |
OK1043 # 05 Y:2021 | 05 | 2021 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $2,008 | $952 | Not Implemented |
OK1043 # 04 Y:2021 | 04 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,397 | $2,946 | Implemented |
TT0241 # 01 Y:2020 | 01 | 2020 | RECOVER WASTE HEAT FROM EQUIPMENT | $116,047 | $13,220 | Not Implemented |
TT0241 # 11 Y:2020 | 11 | 2020 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $307 | $680 | Implemented |
TT0241 # 12 Y:2020 | 12 | 2020 | INSTALL / REPAIR INSULATION ON STEAM LINES | $74 | $269 | Implemented |
TT0241 # 03 Y:2020 | 03 | 2020 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $49,818 | $14,600 | Implemented |
TT0241 # 06 Y:2020 | 06 | 2020 | UPGRADE CONTROLS ON COMPRESSORS | $4,203 | $120 | Not Implemented |
TT0241 # 09 Y:2020 | 09 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,651 | $6,000 | Implemented |
TT0241 # 05 Y:2020 | 05 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,106 | $530 | Implemented |
TT0241 # 07 Y:2020 | 07 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,304 | $3,360 | Implemented |
TT0241 # 04 Y:2020 | 04 | 2020 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $18,441 | $75,000 | Implemented |
TT0241 # 10 Y:2020 | 10 | 2020 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $404 | $1,000 | Implemented |
TT0241 # 02 Y:2020 | 02 | 2020 | UPGRADE CONTROLS ON COMPRESSORS | $54,178 | $300 | Implemented |
TT0241 # 08 Y:2020 | 08 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,202 | $20 | Implemented |
TT0237 # 03 Y:2020 | 03 | 2020 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,785 | $4,720 | Not Implemented |