IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

51

matching recommendations
Reset
SIC 33 Primary Metal Industries
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LM0085 # 10 Y:2004 10 2004 $54,080 $3,320 Implemented
LM0085 # 09 Y:2004 09 2004 $3,360 $1,850 Implemented
LM0085 # 08 Y:2004 08 2004 $18,000 $2,450 Implemented
LM0085 # 07 Y:2004 07 2004 $9,060 $1,500 Implemented
LM0085 # 06 Y:2004 06 2004 $26,300 $4,450 Implemented
LM0085 # 05 Y:2004 05 2004 ADJUST BURNERS FOR EFFICIENT OPERATION $5,902 $600 Implemented
LM0085 # 04 Y:2004 04 2004 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING $1,335 $741 Not Implemented
LM0085 # 01 Y:2004 01 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,324 $205 Implemented
LM0085 # 02 Y:2004 02 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $167 $0 Implemented
LM0085 # 03 Y:2004 03 2004 CLEAN FOULING FROM WATER LINES REGULARLY $2,852 $180 Implemented
SF0289 # 07 Y:2004 07 2004 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $3,506 $6,000 Not Implemented
SF0289 # 10 Y:2004 10 2004 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $7,873 $100 Not Implemented
SF0289 # 04 Y:2004 04 2004 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $864 $1,183 Not Implemented
SF0289 # 05 Y:2004 05 2004 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $8,525 $12,060 Not Implemented
SF0289 # 03 Y:2004 03 2004 INSTALL OCCUPANCY SENSORS $1,280 $1,280 Not Implemented
SF0289 # 09 Y:2004 09 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $449 $960 Not Implemented
SF0289 # 01 Y:2004 01 2004 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE $2,527 $2,527 Implemented
SF0289 # 02 Y:2004 02 2004 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING $956 $180 Implemented
SF0289 # 08 Y:2004 08 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,750 $6,748 Implemented
SF0289 # 06 Y:2004 06 2004 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $270 $885 Implemented
LM0080 # 01 Y:2004 01 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $621 $475 Implemented
LM0080 # 03 Y:2004 03 2004 ADJUST BURNERS FOR EFFICIENT OPERATION $537 $0 Implemented
LM0080 # 04 Y:2004 04 2004 $28,600 $20,592 Not Implemented
LM0080 # 05 Y:2004 05 2004 $3,467 $6,000 Not Implemented
LM0080 # 06 Y:2004 06 2004 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $23,164 $300 Implemented