Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
110
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0596 # 04 Y:2006 | 04 | 2006 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $3,810 | $1,000 | Implemented |
CO0596 # 07 Y:2006 | 07 | 2006 | USE SOLAR HEAT TO MAKE ELECTRICTY | $1,100 | $2,950 | Not Implemented |
CO0596 # 02 Y:2006 | 02 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,270 | $33,120 | Implemented |
CO0596 # 08 Y:2006 | 08 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $910 | $5,740 | Implemented |
CO0596 # 01 Y:2006 | 01 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $244 | $1,008 | Implemented |
CO0596 # 06 Y:2006 | 06 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,120 | $9,260 | Implemented |
CO0596 # 03 Y:2006 | 03 | 2006 | INCREASE EFFICIENCY OF TRUCKS | $5,740 | $0 | Implemented |
CO0596 # 05 Y:2006 | 05 | 2006 | ADD AREA LIGHTING SWITCHES | $2,410 | $100 | Not Implemented |
CO0594 # 04 Y:2006 | 04 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $150 | $442 | Not Implemented |
CO0594 # 05 Y:2006 | 05 | 2006 | TURN OFF EQUIPMENT WHEN NOT IN USE | $380 | $0 | Not Implemented |
CO0594 # 07 Y:2006 | 07 | 2006 | USE SOLAR HEAT TO MAKE ELECTRICTY | $1,100 | $2,950 | Not Implemented |
CO0594 # 08 Y:2006 | 08 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $990 | $3,420 | Not Implemented |
CO0594 # 06 Y:2006 | 06 | 2006 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,200 | $5,050 | Not Implemented |
CO0594 # 09 Y:2006 | 09 | 2006 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $950 | $500 | Not Implemented |
CO0594 # 03 Y:2006 | 03 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,300 | $6,900 | Not Implemented |
CO0594 # 01 Y:2006 | 01 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,730 | $3,350 | Not Implemented |
CO0594 # 02 Y:2006 | 02 | 2006 | OPTIMIZE PLANT POWER FACTOR | $4,550 | $11,320 | Not Implemented |
CO0594 # 10 Y:2006 | 10 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $360 | $90 | Not Implemented |
CO0593 # 04 Y:2006 | 04 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,190 | $1,402 | Not Implemented |
CO0593 # 06 Y:2006 | 06 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,030 | $1,920 | Not Implemented |
CO0593 # 03 Y:2006 | 03 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,750 | $120 | Implemented |
CO0593 # 02 Y:2006 | 02 | 2006 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $6,180 | $60 | Implemented |
CO0593 # 05 Y:2006 | 05 | 2006 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,790 | $6,950 | Not Implemented |
CO0593 # 01 Y:2006 | 01 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $22,910 | $60,580 | Not Implemented |
CO0593 # 07 Y:2006 | 07 | 2006 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $1,550 | $6,000 | Implemented |