IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

119

matching recommendations
Reset
NAICS 3222 Converted Paper Product Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UF0391 # 13 Y:2006 13 2006 TURN OFF EQUIPMENT WHEN NOT IN USE $63,455 $0 Not Implemented
UF0391 # 14 Y:2006 14 2006 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $83,200 $5,350 Not Implemented
UF0391 # 15 Y:2006 15 2006 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $17,472 $0 Not Implemented
UF0391 # 16 Y:2006 16 2006 $10,320 $0 Not Implemented
MI0114 # 01 Y:2005 01 2005 INSULATE BARE EQUIPMENT $28,126 $1,091 Not Implemented
MI0114 # 02 Y:2005 02 2005 IMPROVE COMBUSTION CONTROL CAPABILITY $20,574 $30,050 Implemented
MI0114 # 03 Y:2005 03 2005 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $28,927 $27,000 Not Implemented
MI0114 # 04 Y:2005 04 2005 INSULATE BARE EQUIPMENT $2,983 $225 Implemented
MI0114 # 05 Y:2005 05 2005 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $9,790 $4,360 Implemented
MI0114 # 06 Y:2005 06 2005 TURN OFF EQUIPMENT WHEN NOT IN USE $9,392 $77 Implemented
MI0114 # 07 Y:2005 07 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,896 $1,074 Implemented
MI0114 # 08 Y:2005 08 2005 UPGRADE CONTROLS ON COMPRESSORS $3,882 $0 Implemented
MI0114 # 09 Y:2005 09 2005 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $3,521 $4,628 Not Implemented
UF0335 # 01 Y:2004 01 2004 ADD AREA LIGHTING SWITCHES $2,525 $10,670 Not Implemented
UF0335 # 02 Y:2004 02 2004 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $44,300 $205,000 Not Implemented
UF0335 # 03 Y:2004 03 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $26,089 $41,729 Implemented
UF0335 # 04 Y:2004 04 2004 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $7,790 $13,573 Implemented
UF0335 # 05 Y:2004 05 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,008 $0 Not Implemented
UF0335 # 06 Y:2004 06 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,359 $376 Implemented
UF0335 # 07 Y:2004 07 2004 OPTIMIZE PLANT POWER FACTOR $3,237 $20,000 Implemented
MI0061 # 01 Y:2003 01 2003 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $2,497 $8,673 Not Implemented
MI0061 # 02 Y:2003 02 2003 TURN OFF EQUIPMENT WHEN NOT IN USE $3,605 $169 Not Implemented
MI0061 # 03 Y:2003 03 2003 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $974 $332 Implemented
MI0061 # 04 Y:2003 04 2003 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $2,962 $6 Implemented
MI0061 # 05 Y:2003 05 2003 INSTALL OCCUPANCY SENSORS $524 $111 Implemented