Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
266
matching recommendationsSIC | 33 | Primary Metal Industries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0596 # 04 Y:2023 | 04 | 2023 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $213,087 | $0 | Implemented |
UF0596 # 11 Y:2023 | 11 | 2023 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $3,156 | $2,352 | Implemented |
UF0596 # 07 Y:2023 | 07 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $47,000 | $171,903 | Implemented |
UF0596 # 02 Y:2023 | 02 | 2023 | INSTALL SUB-METERING EQUIPMENT | $266,539 | $15,232 | Implemented |
UF0596 # 05 Y:2023 | 05 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $145,162 | $141,225 | Implemented |
UF0596 # 03 Y:2023 | 03 | 2023 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $232,670 | $300,000 | Implemented |
UF0596 # 10 Y:2023 | 10 | 2023 | IMPROVE SPACE COMFORT CONDITIONING | $26,447 | $4,768 | Implemented |
UF0596 # 01 Y:2023 | 01 | 2023 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $1,546,439 | $3,990,000 | Not Implemented |
UF0596 # 06 Y:2023 | 06 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $50,904 | $49,563 | Implemented |
UF0596 # 08 Y:2023 | 08 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $27,499 | $1,399 | Implemented |
UF0596 # 09 Y:2023 | 09 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $12,289 | $25,440 | Implemented |
UF0595 # 10 Y:2023 | 10 | 2023 | IMPROVE SPACE COMFORT CONDITIONING | $20,697 | $4,480 | Implemented |
UF0595 # 06 Y:2023 | 06 | 2023 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $2,957 | $3,276 | Implemented |
UF0595 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,458 | $356 | Implemented |
UF0595 # 09 Y:2023 | 09 | 2023 | INSTALL OCCUPANCY SENSORS | $1,092 | $2,160 | Implemented |
UF0595 # 03 Y:2023 | 03 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $18,931 | $25,400 | Implemented |
UF0595 # 08 Y:2023 | 08 | 2023 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $1,317 | $5,838 | Implemented |
UF0595 # 02 Y:2023 | 02 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $39,683 | $20,785 | Implemented |
UF0595 # 04 Y:2023 | 04 | 2023 | USER BATTERY STORAGE FOR POWER QUALITY ISSUES | $6,261 | $20,000 | Not Implemented |
UF0595 # 07 Y:2023 | 07 | 2023 | INSTALL SUB-METERING EQUIPMENT | $1,589 | $4,340 | Implemented |
UF0595 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $95,368 | $289,896 | Not Implemented |
GT0937 # 05 Y:2019 | 05 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $17,740 | $158,500 | Not Implemented |
GT0937 # 04 Y:2019 | 04 | 2019 | RECOVER WASTE HEAT FROM EQUIPMENT | $32,772 | $100,000 | Not Implemented |
GT0937 # 03 Y:2019 | 03 | 2019 | OPTIMIZE PLANT POWER FACTOR | $10,618 | $38,920 | Not Implemented |
GT0937 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,545 | $4,311 | Implemented |