Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
40
matching recommendationsSIC | 35 | Industrial Machinery And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0025 # 05 Y:2001 | 05 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $694 | $1,778 | Implemented |
MI0025 # 04 Y:2001 | 04 | 2001 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $1,050 | $100 | Implemented |
MI0025 # 03 Y:2001 | 03 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $492 | $2 | Not Implemented |
MI0025 # 02 Y:2001 | 02 | 2001 | ELIMINATE A BY-PRODUCT | $35,000 | $100 | Not Implemented |
MI0025 # 01 Y:2001 | 01 | 2001 | RECOVER MECHANICAL ENERGY | $165,750 | $15,000 | Not Implemented |
UF0279 # 08 Y:2001 | 08 | 2001 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $1,800 | $0 | Implemented |
UF0279 # 01 Y:2001 | 01 | 2001 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,057 | $10,208 | Implemented |
UF0279 # 03 Y:2001 | 03 | 2001 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $20,871 | $62,226 | Not Implemented |
UF0279 # 04 Y:2001 | 04 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,241 | $1,520 | Implemented |
UF0279 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $696 | $660 | Not Implemented |
UF0279 # 09 Y:2001 | 09 | 2001 | INSTALL AUTOMATIC PART STORAGE / RETREVAL SYSTEM | $6,500 | $4,612 | Implemented |
UF0279 # 06 Y:2001 | 06 | 2001 | INSTALL SKYLIGHTS | $2,897 | $3,188 | Not Implemented |
UF0279 # 07 Y:2001 | 07 | 2001 | INSTALL OCCUPANCY SENSORS | $2,853 | $767 | Implemented |
UF0279 # 05 Y:2001 | 05 | 2001 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,260 | $0 | Implemented |
UF0275 # 08 Y:2001 | 08 | 2001 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $11,648 | $50 | Implemented |
UF0275 # 10 Y:2001 | 10 | 2001 | $27,670 | $1,800 | Implemented | |
UF0275 # 11 Y:2001 | 11 | 2001 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $165,000 | $42,000 | Implemented |
UF0275 # 09 Y:2001 | 09 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $15,233 | $8,000 | Not Implemented |
UF0275 # 07 Y:2001 | 07 | 2001 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $36,614 | $72,000 | Not Implemented |
UF0275 # 01 Y:2001 | 01 | 2001 | INSTALL COMMON HEADER ON COMPRESSORS | $4,038 | $4,300 | Not Implemented |
UF0275 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,164 | $3,861 | Not Implemented |
UF0275 # 03 Y:2001 | 03 | 2001 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $6,334 | $30,000 | Not Implemented |
UF0275 # 04 Y:2001 | 04 | 2001 | USE PHOTOCELL CONTROLS | $7,800 | $25,000 | Implemented |
UF0275 # 05 Y:2001 | 05 | 2001 | $1,753 | $1,025 | Not Implemented | |
UF0275 # 06 Y:2001 | 06 | 2001 | KEEP EQUIPMENT CLEAN | $1,578 | $252 | Implemented |