Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
129
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0724 # 10 Y:2005 | 10 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,915 | $0 | Not Implemented |
UD0724 # 04 Y:2005 | 04 | 2005 | INSULATE BARE EQUIPMENT | $13,563 | $6,505 | Implemented |
UD0724 # 09 Y:2005 | 09 | 2005 | CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN | $3,364 | $0 | Implemented |
UD0724 # 06 Y:2005 | 06 | 2005 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,922 | $4,800 | Not Implemented |
UD0724 # 01 Y:2005 | 01 | 2005 | USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS | $59,198 | $30,000 | Not Implemented |
UD0724 # 11 Y:2005 | 11 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $471 | $880 | Implemented |
UD0724 # 07 Y:2005 | 07 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,199 | $7,500 | Not Implemented |
UD0724 # 03 Y:2005 | 03 | 2005 | USE PHOTOCELL CONTROLS | $16,400 | $0 | Implemented |
UD0724 # 05 Y:2005 | 05 | 2005 | SEPARATE CONTROLS OF AIR HANDLERS FROM AC/ HEATING SYSTEMS | $9,550 | $530 | Not Implemented |
UD0724 # 02 Y:2005 | 02 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $33,240 | $102,000 | Not Implemented |
UD0724 # 08 Y:2005 | 08 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,477 | $0 | Not Implemented |
UD0723 # 04 Y:2005 | 04 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,315 | $13,340 | Implemented |
UD0723 # 05 Y:2005 | 05 | 2005 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $6,126 | $7,000 | Implemented |
UD0723 # 03 Y:2005 | 03 | 2005 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $7,394 | $0 | Not Implemented |
UD0723 # 10 Y:2005 | 10 | 2005 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $2,730 | $0 | Not Implemented |
UD0723 # 08 Y:2005 | 08 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,309 | $0 | Implemented |
UD0723 # 15 Y:2005 | 15 | 2005 | UPGRADE CONTROLS ON COMPRESSORS | $522 | $0 | Implemented |
UD0723 # 07 Y:2005 | 07 | 2005 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $4,573 | $0 | Implemented |
UD0723 # 14 Y:2005 | 14 | 2005 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $840 | $0 | Not Implemented |
UD0723 # 06 Y:2005 | 06 | 2005 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $5,470 | $0 | Not Implemented |
UD0723 # 11 Y:2005 | 11 | 2005 | INSULATE BARE EQUIPMENT | $2,650 | $2,629 | Implemented |
UD0723 # 01 Y:2005 | 01 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,840 | $65,105 | Implemented |
UD0723 # 09 Y:2005 | 09 | 2005 | REDUCE WATER USE WITH COUNTER CURRENT RINSING | $3,070 | $2,000 | Not Implemented |
UD0723 # 12 Y:2005 | 12 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,164 | $0 | Implemented |
UD0723 # 13 Y:2005 | 13 | 2005 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $1,423 | $500 | Not Implemented |