IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

56

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0828 # 06 Y:2012 06 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $8,514 $54,333 Not Implemented
OK0828 # 12 Y:2012 12 2012 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $13,502 $139,769 Not Implemented
OK0828 # 11 Y:2012 11 2012 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE $14,142 $35,000 Not Implemented
OK0828 # 10 Y:2012 10 2012 INSTALL SET-BACK TIMERS $1,768 $957 Not Implemented
OK0828 # 05 Y:2012 05 2012 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $807 $1,615 Not Implemented
OK0828 # 04 Y:2012 04 2012 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $861 $1,822 Implemented
OK0828 # 03 Y:2012 03 2012 RECOVER WASTE HEAT FROM EQUIPMENT $2,911 $4,506 Not Implemented
OK0828 # 02 Y:2012 02 2012 RECOVER WASTE HEAT FROM EQUIPMENT $3,671 $3,025 Not Implemented
OK0828 # 01 Y:2012 01 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,556 $1,400 Implemented
OK0828 # 13 Y:2012 13 2012 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $3,427 $1,515 Implemented
OK0828 # 07 Y:2012 07 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,604 $30,015 Not Implemented
OK0828 # 08 Y:2012 08 2012 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $12,840 $23,750 Not Implemented
OK0828 # 09 Y:2012 09 2012 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $3,664 $14,850 Not Implemented
OK0828 # 14 Y:2012 14 2012 OPTIMIZE PLANT POWER FACTOR $3,494 $8,250 Not Implemented
OK0827 # 07 Y:2012 07 2012 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $4,564 $22,440 Not Implemented
OK0827 # 02 Y:2012 02 2012 RECOVER WASTE HEAT FROM EQUIPMENT $2,407 $1,378 Implemented
OK0827 # 08 Y:2012 08 2012 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $4,021 $17,592 Not Implemented
OK0827 # 12 Y:2012 12 2012 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $1,889 $7,800 Not Implemented
OK0827 # 14 Y:2012 14 2012 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $2,878 $36,395 Implemented
OK0827 # 04 Y:2012 04 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,418 $10,765 Implemented
OK0827 # 06 Y:2012 06 2012 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $13,788 $23,625 Not Implemented
OK0827 # 01 Y:2012 01 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,533 $1,000 Implemented
OK0827 # 10 Y:2012 10 2012 INSTALL SET-BACK TIMERS $2,711 $0 Implemented
OK0827 # 11 Y:2012 11 2012 OPTIMIZE PLANT POWER FACTOR $7,070 $17,506 Not Implemented
OK0827 # 03 Y:2012 03 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,484 $0 Implemented