IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

115

matching recommendations
Reset
SIC 209 Misc. Food And Kindred Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LS2112 # 06 Y:2021 06 2021 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $285 $445 Not Implemented
LS2106 # 01 Y:2021 01 2021 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $169 $25 Implemented
LS2106 # 02 Y:2021 02 2021 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $1,804 $300 Implemented
LS2106 # 03 Y:2021 03 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,586 $585 Implemented
LS2106 # 04 Y:2021 04 2021 INSTALL AUTOMATIC PACKING EQUIPMENT $109,280 $30,730 Not Implemented
LS2106 # 05 Y:2021 05 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $563 $363 Implemented
LS2106 # 06 Y:2021 06 2021 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $202 $427 Not Implemented
LS1903 # 01 Y:2019 01 2019 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $1,079 $150 Not Implemented
LS1903 # 02 Y:2019 02 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $135 $0 Implemented
LS1903 # 03 Y:2019 03 2019 IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS $839 $0 Implemented
LS1903 # 04 Y:2019 04 2019 INSTALL / REPAIR INSULATION ON STEAM LINES $480 $240 Not Implemented
LS1903 # 05 Y:2019 05 2019 TURN OFF EQUIPMENT WHEN NOT IN USE $45 $0 Implemented
LS1903 # 06 Y:2019 06 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,445 $2,189 Not Implemented
LS0012 # 01 Y:2017 01 2017 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $28,766 $12,000 Not Implemented
LS0012 # 02 Y:2017 02 2017 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $2,205 $920 Not Implemented
LS0012 # 03 Y:2017 03 2017 INSULATE BARE EQUIPMENT $993 $548 Not Implemented
LS0012 # 04 Y:2017 04 2017 IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS $21,748 $15,200 Not Implemented
LS0012 # 05 Y:2017 05 2017 REDUCE EXCESSIVE BOILER BLOWDOWN $3,685 $4,250 Not Implemented
LS0012 # 06 Y:2017 06 2017 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD $28,215 $80,000 Not Implemented
LL0302 # 01 Y:2008 01 2008 AIR CONDITION ONLY SPACE NECESSARY $14,663 $30 Implemented
LL0302 # 02 Y:2008 02 2008 INSULATE BARE EQUIPMENT $10,611 $75,579 Not Implemented
LL0302 # 03 Y:2008 03 2008 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $7,364 $450 Implemented
LL0302 # 04 Y:2008 04 2008 INSULATE BARE EQUIPMENT $6,658 $38,670 Not Implemented
LL0302 # 05 Y:2008 05 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $788 $59 Not Implemented
LL0302 # 06 Y:2008 06 2008 INSTALL OCCUPANCY SENSORS $320 $240 Not Implemented