Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
54
matching recommendationsSIC | 22 | Textile Mill Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
ME0218 # 01 Y:1997 | 01 | 1997 | $54,750 | $10,120 | Implemented | |
ME0218 # 05 Y:1997 | 05 | 1997 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,711 | $3,950 | Not Implemented |
ME0218 # 04 Y:1997 | 04 | 1997 | USE OPTIMUM THICKNESS INSULATION | $2,188 | $1,640 | Not Implemented |
ME0218 # 06 Y:1997 | 06 | 1997 | $11,213 | $1,400 | Implemented | |
ME0218 # 07 Y:1997 | 07 | 1997 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $3,300 | $0 | Not Implemented |
ME0218 # 08 Y:1997 | 08 | 1997 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $580 | $1,840 | Not Implemented |
ME0218 # 09 Y:1997 | 09 | 1997 | MINIMIZE WATER USAGE | $412 | $0 | Not Implemented |
ME0218 # 03 Y:1997 | 03 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,379 | $15,318 | Not Implemented |
ME0218 # 02 Y:1997 | 02 | 1997 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $9,110 | $20,420 | Not Implemented |
ME0214 # 08 Y:1997 | 08 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $387 | $30 | Implemented |
ME0214 # 07 Y:1997 | 07 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $604 | $0 | Not Implemented |
ME0214 # 06 Y:1997 | 06 | 1997 | USE OPTIMUM THICKNESS INSULATION | $816 | $75 | Implemented |
ME0214 # 05 Y:1997 | 05 | 1997 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,351 | $0 | Implemented |
ME0214 # 04 Y:1997 | 04 | 1997 | $2,400 | $800 | Not Implemented | |
ME0214 # 03 Y:1997 | 03 | 1997 | $4,000 | $2,840 | Implemented | |
ME0214 # 02 Y:1997 | 02 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,079 | $31,719 | Implemented |
ME0214 # 01 Y:1997 | 01 | 1997 | $24,500 | $7,500 | Implemented | |
ME0214 # 10 Y:1997 | 10 | 1997 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $3,432 | $6,200 | Not Implemented |
ME0214 # 09 Y:1997 | 09 | 1997 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $832 | $6,200 | Implemented |
ME0212 # 02 Y:1997 | 02 | 1997 | COVER OPEN TANKS | $6,034 | $6,233 | Not Implemented |
ME0212 # 03 Y:1997 | 03 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,766 | $13,215 | Implemented |
ME0212 # 08 Y:1997 | 08 | 1997 | REPAIR AND ELIMINATE STEAM LEAKS | $8,286 | $9,600 | Not Implemented |
ME0212 # 05 Y:1997 | 05 | 1997 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,178 | $1,632 | Implemented |
ME0212 # 07 Y:1997 | 07 | 1997 | ISOLATE STEAM LINES TO AVOID HEATING AIR CONDITIONED AREAS | $849 | $439 | Implemented |
ME0212 # 09 Y:1997 | 09 | 1997 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $1,950 | $5,000 | Not Implemented |