Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
122
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0294 # 06 Y:2005 | 06 | 2005 | INSULATE BARE EQUIPMENT | $1,231 | $1,344 | Not Implemented |
UM0294 # 03 Y:2005 | 03 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,684 | $4,536 | Not Implemented |
UM0294 # 05 Y:2005 | 05 | 2005 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $1,604 | $3,000 | Not Implemented |
UM0294 # 01 Y:2005 | 01 | 2005 | COVER OPEN TANKS | $48,559 | $7,232 | Not Implemented |
UM0294 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,274 | $600 | Not Implemented |
UM0294 # 04 Y:2005 | 04 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $3,051 | $2,400 | Not Implemented |
UM0293 # 05 Y:2005 | 05 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,239 | $0 | Not Implemented |
UM0293 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,506 | $175 | Implemented |
UM0293 # 01 Y:2005 | 01 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,861 | $18,165 | Implemented |
UM0293 # 04 Y:2005 | 04 | 2005 | OPTIMIZE PLANT POWER FACTOR | $3,999 | $2,728 | Not Implemented |
UM0293 # 03 Y:2005 | 03 | 2005 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $6,085 | $50 | Implemented |
UM0293 # 06 Y:2005 | 06 | 2005 | COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER | $227 | $200 | Implemented |
UM0292 # 02 Y:2005 | 02 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $5,368 | $5,000 | Implemented |
UM0292 # 01 Y:2005 | 01 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,731 | $23,005 | Not Implemented |
UM0292 # 03 Y:2005 | 03 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,782 | $480 | Implemented |
UM0292 # 06 Y:2005 | 06 | 2005 | INSTALL OCCUPANCY SENSORS | $821 | $368 | Not Implemented |
UM0292 # 04 Y:2005 | 04 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,943 | $50 | Implemented |
UM0292 # 05 Y:2005 | 05 | 2005 | RESCHEDULE AND REARRANGE MULTIPLE-SOURCE HEATING SYSTEMS | $1,193 | $3,000 | Not Implemented |
UM0291 # 01 Y:2005 | 01 | 2005 | RECOVER WASTE HEAT FROM EQUIPMENT | $20,293 | $9,000 | Implemented |
UM0291 # 02 Y:2005 | 02 | 2005 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $18,138 | $19,073 | Not Implemented |
UM0291 # 03 Y:2005 | 03 | 2005 | COVER OPEN TANKS | $4,518 | $2,366 | Implemented |
UM0291 # 04 Y:2005 | 04 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,427 | $1,900 | Implemented |
UM0291 # 05 Y:2005 | 05 | 2005 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,841 | $1,490 | Not Implemented |
UM0291 # 08 Y:2005 | 08 | 2005 | INSTALL OCCUPANCY SENSORS | $396 | $150 | Not Implemented |
UM0291 # 06 Y:2005 | 06 | 2005 | USE DOUBLE OR TRIPLE GLAZED WINDOWS TO MAINTAIN HIGHER RELATIVE HUMIDITY AND TO REDUCE HEAT LOSSES | $2,309 | $39,000 | Not Implemented |