Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
26
matching recommendationsSIC | 25 | Furniture And Fixtures |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0189 # 10 Y:2001 | 10 | 2001 | $98,125 | $100,000 | Not Implemented | |
MS0189 # 09 Y:2001 | 09 | 2001 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $57,988 | $72,000 | Not Implemented |
MS0189 # 08 Y:2001 | 08 | 2001 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $1,638 | $4,046 | Implemented |
MS0189 # 07 Y:2001 | 07 | 2001 | INSULATE BARE EQUIPMENT | $78 | $112 | Implemented |
MS0189 # 06 Y:2001 | 06 | 2001 | COMBINE UTILITY METERS | $114 | $212 | Not Implemented |
MS0189 # 05 Y:2001 | 05 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $171 | $128 | Implemented |
MS0189 # 04 Y:2001 | 04 | 2001 | DISCONNECT BALLASTS | $286 | $540 | Implemented |
MS0189 # 03 Y:2001 | 03 | 2001 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $3,255 | $1,550 | Not Implemented |
MS0189 # 02 Y:2001 | 02 | 2001 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $3,426 | $2,725 | Not Implemented |
MS0189 # 01 Y:2001 | 01 | 2001 | USE RADIANT HEATER FOR SPOT HEATING | $20,927 | $3,216 | Not Implemented |
MS0183 # 04 Y:2001 | 04 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $711 | $2,074 | Not Implemented |
MS0183 # 06 Y:2001 | 06 | 2001 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $1,296 | $50 | Not Implemented |
MS0183 # 05 Y:2001 | 05 | 2001 | CONVERT FROM BATCH OPERATION TO CONTINUOUS PROCESSING | $1,957 | $432 | Not Implemented |
MS0183 # 03 Y:2001 | 03 | 2001 | INSTALL OCCUPANCY SENSORS | $142 | $230 | Not Implemented |
MS0183 # 02 Y:2001 | 02 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,000 | $190 | Implemented |
MS0183 # 01 Y:2001 | 01 | 2001 | OPTIMIZE PLANT POWER FACTOR | $7,236 | $8,235 | Not Implemented |
MS0182 # 05 Y:2001 | 05 | 2001 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $91 | $0 | Implemented |
MS0182 # 04 Y:2001 | 04 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $210 | $195 | Not Implemented |
MS0182 # 03 Y:2001 | 03 | 2001 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $647 | $54 | Implemented |
MS0182 # 02 Y:2001 | 02 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,201 | $427 | Implemented |
MS0182 # 01 Y:2001 | 01 | 2001 | OPTIMIZE PLANT POWER FACTOR | $2,138 | $2,205 | Not Implemented |
MS0181 # 01 Y:2001 | 01 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $282 | $107 | Not Implemented |
MS0181 # 05 Y:2001 | 05 | 2001 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,332 | $2,100 | Not Implemented |
MS0181 # 04 Y:2001 | 04 | 2001 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,627 | $0 | Not Implemented |
MS0181 # 03 Y:2001 | 03 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $672 | $104 | Implemented |