Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
24
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0175 # 05 Y:2000 | 05 | 2000 | OPTIMIZE PLANT POWER FACTOR | $1,336 | $2,385 | Not Implemented |
MS0175 # 04 Y:2000 | 04 | 2000 | INSULATE BARE EQUIPMENT | $55 | $147 | Not Implemented |
MS0175 # 03 Y:2000 | 03 | 2000 | DISCONNECT BALLASTS | $272 | $426 | Not Implemented |
MS0175 # 02 Y:2000 | 02 | 2000 | USE PHOTOCELL CONTROLS | $433 | $186 | Not Implemented |
MS0175 # 01 Y:2000 | 01 | 2000 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $13,400 | $50 | Implemented |
MS0174 # 01 Y:2000 | 01 | 2000 | OPTIMIZE PLANT POWER FACTOR | $7,319 | $6,300 | Not Implemented |
MS0174 # 07 Y:2000 | 07 | 2000 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $211 | $0 | Not Implemented |
MS0174 # 06 Y:2000 | 06 | 2000 | INSULATE BARE EQUIPMENT | $368 | $156 | Not Implemented |
MS0174 # 05 Y:2000 | 05 | 2000 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $24,750 | $68,250 | Not Implemented |
MS0174 # 04 Y:2000 | 04 | 2000 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,584 | $3,339 | Not Implemented |
MS0174 # 03 Y:2000 | 03 | 2000 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $159 | $60 | Not Implemented |
MS0174 # 02 Y:2000 | 02 | 2000 | USE PHOTOCELL CONTROLS | $243 | $148 | Not Implemented |
MS0168 # 01 Y:2000 | 01 | 2000 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,988 | $50 | Not Implemented |
MS0168 # 08 Y:2000 | 08 | 2000 | $394 | $50 | Not Implemented | |
MS0168 # 07 Y:2000 | 07 | 2000 | $5,437 | $50 | Not Implemented | |
MS0168 # 06 Y:2000 | 06 | 2000 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,440 | $2,080 | Not Implemented |
MS0168 # 05 Y:2000 | 05 | 2000 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $28,070 | $5,275 | Not Implemented |
MS0168 # 04 Y:2000 | 04 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $62 | $167 | Implemented |
MS0168 # 03 Y:2000 | 03 | 2000 | INSTALL TIMERS AND/OR THERMOSTATS | $231 | $472 | Implemented |
MS0168 # 02 Y:2000 | 02 | 2000 | OPTIMIZE PLANT POWER FACTOR | $1,393 | $1,710 | Implemented |
MS0161 # 04 Y:2000 | 04 | 2000 | BURN WASTE OIL FOR HEAT | $1,062 | $2,067 | Not Implemented |
MS0161 # 03 Y:2000 | 03 | 2000 | AIR CONDITION ONLY SPACE NECESSARY | $6,113 | $3,530 | Not Implemented |
MS0161 # 02 Y:2000 | 02 | 2000 | USE SYNTHETIC LUBRICANT | $7,432 | $660 | Implemented |
MS0161 # 01 Y:2000 | 01 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $6,141 | $1,870 | Not Implemented |