IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

29

matching recommendations
Reset
SIC 3089 Plastics Products, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MZ0302 # 03 Y:2020 03 2020 INSULATE BARE EQUIPMENT $251 $226 Not Implemented
MZ0302 # 02 Y:2020 02 2020 RECOVER WASTE HEAT FROM EQUIPMENT $19,767 $14,500 Not Implemented
MZ0302 # 05 Y:2020 05 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $32,817 $55,992 Implemented
MZ0302 # 01 Y:2020 01 2020 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,015 $4,700 Implemented
MZ0302 # 04 Y:2020 04 2020 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $217 $45 Implemented
MZ0302 # 06 Y:2020 06 2020 INSTALL OCCUPANCY SENSORS $2,138 $1,800 Not Implemented
MZ0293 # 09 Y:2020 09 2020 RECOVER WASTE HEAT FROM EQUIPMENT $11,186 $28,360 Not Implemented
MZ0293 # 08 Y:2020 08 2020 OPTIMIZE PLANT POWER FACTOR $328,879 $538,653 Implemented
MZ0293 # 07 Y:2020 07 2020 UTILIZE A LESS EXPENSIVE COOLING METHOD $7,010 $25,500 Not Implemented
MZ0293 # 06 Y:2020 06 2020 INSTALL OCCUPANCY SENSORS $230 $780 Implemented
MZ0293 # 05 Y:2020 05 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $63,762 $88,053 Implemented
MZ0293 # 04 Y:2020 04 2020 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,596 $4,100 Not Implemented
MZ0293 # 03 Y:2020 03 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,924 $910 Implemented
MZ0293 # 01 Y:2020 01 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,827 $320 Implemented
MZ0293 # 02 Y:2020 02 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,246 $6,782 Implemented
MZ0290 # 07 Y:2020 07 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $767 $1,272 Not Implemented
MZ0290 # 06 Y:2020 06 2020 INSTALL OCCUPANCY SENSORS $1,134 $4,935 Implemented
MZ0290 # 05 Y:2020 05 2020 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,411 $298 Implemented
MZ0290 # 04 Y:2020 04 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,247 $2,264 Implemented
MZ0290 # 03 Y:2020 03 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,559 $1,091 Implemented
MZ0290 # 02 Y:2020 02 2020 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,851 $3,250 Not Implemented
MZ0290 # 01 Y:2020 01 2020 UPGRADE CONTROLS ON COMPRESSORS $4,714 $3,096 Implemented
MZ0289 # 06 Y:2020 06 2020 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,118 $270 Implemented
MZ0289 # 05 Y:2020 05 2020 INSTALL OCCUPANCY SENSORS $2,151 $7,144 Implemented
MZ0289 # 03 Y:2020 03 2020 USE OPTIMUM THICKNESS INSULATION $3,128 $4,056 Implemented