Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
30
matching recommendationsSIC | 24 | Lumber And Wood Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0167 # 04 Y:1999 | 04 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,229 | $5,323 | Implemented |
NC0167 # 03 Y:1999 | 03 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $489 | $1,100 | Not Implemented |
NC0167 # 02 Y:1999 | 02 | 1999 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $6,230 | $19,535 | Not Implemented |
NC0167 # 01 Y:1999 | 01 | 1999 | ADJUST BURNERS FOR EFFICIENT OPERATION | $1,244 | $2,400 | Implemented |
NC0167 # 05 Y:1999 | 05 | 1999 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $503 | $143 | Implemented |
NC0167 # 06 Y:1999 | 06 | 1999 | BURN WOOD BY-PRODUCTS FOR HEAT | $22,545 | $80,500 | Not Implemented |
NC0167 # 07 Y:1999 | 07 | 1999 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $43,740 | $9,500 | Not Implemented |
NC0167 # 08 Y:1999 | 08 | 1999 | $25,000 | $1,000 | Implemented | |
NC0166 # 08 Y:1999 | 08 | 1999 | USE DISTILLATION, EVAPORATION TO REMOVE CONTAMINANTS | $29,365 | $82,000 | Not Implemented |
NC0166 # 10 Y:1999 | 10 | 1999 | $7,700 | $1,000 | Implemented | |
NC0166 # 09 Y:1999 | 09 | 1999 | $14,000 | $15,500 | Implemented | |
NC0166 # 07 Y:1999 | 07 | 1999 | BURN WOOD BY-PRODUCTS FOR HEAT | $12,902 | $62,200 | Not Implemented |
NC0166 # 06 Y:1999 | 06 | 1999 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $645 | $800 | Not Implemented |
NC0166 # 05 Y:1999 | 05 | 1999 | INSULATE FEEDWATER TANK | $328 | $340 | Implemented |
NC0166 # 04 Y:1999 | 04 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $4,328 | $5,000 | Not Implemented |
NC0166 # 03 Y:1999 | 03 | 1999 | USE PHOTOCELL CONTROLS | $601 | $150 | Implemented |
NC0166 # 02 Y:1999 | 02 | 1999 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $5,877 | $15,000 | Not Implemented |
NC0166 # 01 Y:1999 | 01 | 1999 | RECOVER WASTE HEAT FROM EQUIPMENT | $756 | $1,500 | Implemented |
OD0137 # 02 Y:1999 | 02 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $839 | $400 | Implemented |
OD0137 # 03 Y:1999 | 03 | 1999 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $90 | $100 | Not Implemented |
OD0137 # 04 Y:1999 | 04 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,840 | $1,000 | Implemented |
OD0136 # 06 Y:1999 | 06 | 1999 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $7,187 | $2,200 | Not Implemented |
OD0136 # 05 Y:1999 | 05 | 1999 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,069 | $1,870 | Not Implemented |
OD0136 # 04 Y:1999 | 04 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $622 | $800 | Implemented |
OD0136 # 03 Y:1999 | 03 | 1999 | INSTALL OCCUPANCY SENSORS | $784 | $1,027 | Not Implemented |