Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
119
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0623 # 04 Y:2018 | 04 | 2018 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $6,478 | $16,800 | Implemented |
NC0623 # 01 Y:2018 | 01 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,801 | $500 | Implemented |
NC0623 # 05 Y:2018 | 05 | 2018 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $14,884 | $10,000 | Not Implemented |
NC0623 # 03 Y:2018 | 03 | 2018 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,320 | $1,203 | Implemented |
NC0623 # 02 Y:2018 | 02 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,322 | $900 | Implemented |
NC0623 # 06 Y:2018 | 06 | 2018 | AVOID REWINDING MOTORS MORE THAN TWICE | $38,566 | $70,014 | Not Implemented |
NC0622 # 02 Y:2018 | 02 | 2018 | INSTALL OCCUPANCY SENSORS | $481 | $250 | Implemented |
NC0622 # 08 Y:2018 | 08 | 2018 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $10,727 | $28,500 | Not Implemented |
NC0622 # 04 Y:2018 | 04 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $161 | $450 | Not Implemented |
NC0622 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,812 | $46,617 | Implemented |
NC0622 # 05 Y:2018 | 05 | 2018 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,361 | $6,000 | Not Implemented |
NC0622 # 09 Y:2018 | 09 | 2018 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $15,903 | $500 | Implemented |
NC0622 # 07 Y:2018 | 07 | 2018 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $1,221 | $1,000 | Not Implemented |
NC0622 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,414 | $525 | Implemented |
NC0622 # 06 Y:2018 | 06 | 2018 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,913 | $8,000 | Not Implemented |
NC0616 # 03 Y:2018 | 03 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $505 | $50 | Implemented |
NC0616 # 05 Y:2018 | 05 | 2018 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,999 | $100 | Implemented |
NC0616 # 06 Y:2018 | 06 | 2018 | REDESIGN PROCESS | $7,804 | $10,000 | Not Implemented |
NC0616 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,771 | $43,490 | Implemented |
NC0616 # 04 Y:2018 | 04 | 2018 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $12,380 | $20,000 | Not Implemented |
NC0616 # 09 Y:2018 | 09 | 2018 | AVOID REWINDING MOTORS MORE THAN TWICE | $2,586 | $5,865 | Implemented |
NC0616 # 07 Y:2018 | 07 | 2018 | INSTALL SENSORS TO DETECT DEFECTS | $112,500 | $150,000 | Implemented |
NC0616 # 08 Y:2018 | 08 | 2018 | REDESIGN PROCESS | $36,741 | $2,500 | Implemented |
NC0616 # 02 Y:2018 | 02 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,695 | $225 | Implemented |
NC0616 # 10 Y:2018 | 10 | 2018 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $15,190 | $500 | Not Implemented |