Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
316
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0892 # 08 Y:2013 | 08 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $4,998 | $0 | Implemented |
UD0892 # 09 Y:2013 | 09 | 2013 | USE OPTIMUM THICKNESS INSULATION | $2,546 | $314 | Not Implemented |
UD0892 # 06 Y:2013 | 06 | 2013 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $3,311 | $3,800 | Not Implemented |
WV0477 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $647 | $1,581 | Not Implemented |
WV0477 # 07 Y:2013 | 07 | 2013 | DEVELOP A REPAIR/REPLACE POLICY | $490 | $1,035 | Implemented |
WV0477 # 09 Y:2013 | 09 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $260 | $137 | Implemented |
WV0477 # 10 Y:2013 | 10 | 2013 | INSTALL TIMERS AND/OR THERMOSTATS | $257 | $586 | Not Implemented |
WV0477 # 04 Y:2013 | 04 | 2013 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $1,996 | $1,000 | Not Implemented |
WV0477 # 08 Y:2013 | 08 | 2013 | INSTALL OCCUPANCY SENSORS | $366 | $135 | Implemented |
WV0477 # 03 Y:2013 | 03 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,064 | $3,573 | Not Implemented |
WV0477 # 02 Y:2013 | 02 | 2013 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $2,823 | $6,345 | Not Implemented |
WV0477 # 06 Y:2013 | 06 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $595 | $257 | Implemented |
WV0477 # 01 Y:2013 | 01 | 2013 | INSULATE BARE EQUIPMENT | $3,015 | $2,013 | Implemented |
WV0476 # 07 Y:2013 | 07 | 2013 | AIR CONDITION ONLY SPACE NECESSARY | $643 | $3,920 | Not Implemented |
WV0476 # 09 Y:2013 | 09 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $595 | $1,431 | Implemented |
WV0476 # 11 Y:2013 | 11 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $259 | $140 | Implemented |
WV0476 # 10 Y:2013 | 10 | 2013 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $301 | $90 | Implemented |
WV0476 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $756 | $3,667 | Not Implemented |
WV0476 # 08 Y:2013 | 08 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $621 | $233 | Not Implemented |
WV0476 # 03 Y:2013 | 03 | 2013 | COMBINE UTILITY METERS | $3,940 | $1,800 | Not Implemented |
WV0476 # 02 Y:2013 | 02 | 2013 | INSTALL TIMERS AND/OR THERMOSTATS | $13,346 | $4,200 | Implemented |
WV0476 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,046 | $26,555 | Implemented |
WV0476 # 12 Y:2013 | 12 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $251 | $50 | Implemented |
WV0476 # 05 Y:2013 | 05 | 2013 | RECOVER WASTE HEAT FROM EQUIPMENT | $845 | $1,940 | Implemented |
WV0476 # 04 Y:2013 | 04 | 2013 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,749 | $5,400 | Not Implemented |