IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

860

matching recommendations
Reset
SIC 35 Industrial Machinery And Equipment
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0878 # 11 Y:2014 11 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,371 $13,908 Implemented
OK0878 # 12 Y:2014 12 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $11,570 $55,638 Implemented
OK0878 # 13 Y:2014 13 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $217 $1,073 Not Implemented
OK0878 # 14 Y:2014 14 2014 INSTALL SET-BACK TIMERS $6,234 $1,983 Not Implemented
OK0859 # 01 Y:2013 01 2013 USE EXISTING DAM TO GENERATE ELECTRICITY $12,404 $65,000 Not Implemented
OK0859 # 02 Y:2013 02 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,187 $7,856 Implemented
OK0859 # 03 Y:2013 03 2013 DISCONNECT BALLASTS $342 $900 Not Implemented
OK0859 # 04 Y:2013 04 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $232 $975 Not Implemented
OK0859 # 05 Y:2013 05 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $327 $2,550 Not Implemented
OK0859 # 06 Y:2013 06 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,550 $3,000 Implemented
OK0859 # 07 Y:2013 07 2013 RECOVER WASTE HEAT FROM EQUIPMENT $3,135 $3,356 Not Implemented
OK0859 # 08 Y:2013 08 2013 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS $20,774 $7,707 Not Implemented
OK0859 # 09 Y:2013 09 2013 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $11,338 $4,600 Not Implemented
OK0859 # 10 Y:2013 10 2013 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $17,170 $30,000 Implemented
OK0859 # 11 Y:2013 11 2013 INSTALL SET-BACK TIMERS $1,753 $460 Not Implemented
OK0859 # 12 Y:2013 12 2013 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $3,487 $3,063 Not Implemented
OK0859 # 13 Y:2013 13 2013 REDUCE HEAT GAIN BY WINDOW TINTING $3,200 $6,500 Implemented
OK0859 # 14 Y:2013 14 2013 REDUCE HEAT GAIN BY WINDOW TINTING $372 $0 Implemented
OK0817 # 01 Y:2011 01 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,438 $510 Implemented
OK0817 # 02 Y:2011 02 2011 RECOVER WASTE HEAT FROM EQUIPMENT $1,812 $1,220 Not Implemented
OK0817 # 03 Y:2011 03 2011 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,613 $2,745 Not Implemented
OK0817 # 04 Y:2011 04 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $728 $2,751 Not Implemented
OK0817 # 05 Y:2011 05 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $29,469 $55,540 Not Implemented
OK0817 # 06 Y:2011 06 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $12,965 $47,375 Not Implemented
OK0817 # 07 Y:2011 07 2011 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $5,011 $23,400 Implemented