Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
144
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0901 # 05 Y:2014 | 05 | 2014 | INSTALL TIMERS AND/OR THERMOSTATS | $156 | $606 | Not Implemented |
OK0901 # 06 Y:2014 | 06 | 2014 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $40,018 | $156,997 | Not Implemented |
OK0901 # 04 Y:2014 | 04 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,328 | $24,267 | Not Implemented |
OK0901 # 01 Y:2014 | 01 | 2014 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,026 | $1,766 | Not Implemented |
OK0901 # 03 Y:2014 | 03 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,102 | $1,890 | Not Implemented |
OK0901 # 02 Y:2014 | 02 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,047 | $1,378 | Not Implemented |
OK0898 # 01 Y:2014 | 01 | 2014 | USE RADIANT HEATER FOR SPOT HEATING | $12,191 | $15,000 | Not Implemented |
OK0898 # 09 Y:2014 | 09 | 2014 | INSULATE BARE EQUIPMENT | $90 | $178 | Not Implemented |
OK0898 # 04 Y:2014 | 04 | 2014 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $303 | $270 | Implemented |
OK0898 # 11 Y:2014 | 11 | 2014 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $89,952 | $75,900 | Not Implemented |
OK0898 # 10 Y:2014 | 10 | 2014 | USE OPTIMUM THICKNESS INSULATION | $6,545 | $27,400 | Implemented |
OK0898 # 06 Y:2014 | 06 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,345 | $5,971 | Not Implemented |
OK0898 # 12 Y:2014 | 12 | 2014 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $20,273 | $45,000 | Not Implemented |
OK0898 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,300 | $11,014 | Not Implemented |
OK0898 # 07 Y:2014 | 07 | 2014 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $136 | $463 | Implemented |
OK0898 # 03 Y:2014 | 03 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,132 | $1,689 | Implemented |
OK0898 # 13 Y:2014 | 13 | 2014 | REPLACE TREATED WATER WITH WELL / SURFACE WATER | $10,867 | $27,400 | Not Implemented |
OK0898 # 08 Y:2014 | 08 | 2014 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $1,045 | $1,060 | Not Implemented |
OK0898 # 02 Y:2014 | 02 | 2014 | INSTALL SET-BACK TIMERS | $3,689 | $1,965 | Not Implemented |
OK0896 # 06 Y:2014 | 06 | 2014 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $13,523 | $7,700 | Not Implemented |
OK0896 # 09 Y:2014 | 09 | 2014 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,826 | $9,200 | Not Implemented |
OK0896 # 02 Y:2014 | 02 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,653 | $1,751 | Implemented |
OK0896 # 05 Y:2014 | 05 | 2014 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $9,020 | $43,252 | Not Implemented |
OK0896 # 08 Y:2014 | 08 | 2014 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,458 | $28,800 | Not Implemented |
OK0896 # 01 Y:2014 | 01 | 2014 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,242 | $1,588 | Not Implemented |