IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

86

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0955 # 04 Y:2016 04 2016 TURN OFF EQUIPMENT WHEN NOT IN USE $2,925 $572 Implemented
OK0955 # 09 Y:2016 09 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,370 $11,297 Implemented
OK0955 # 03 Y:2016 03 2016 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $598 $220 Implemented
OK0955 # 08 Y:2016 08 2016 INSTALL OCCUPANCY SENSORS $8,841 $4,680 Not Implemented
OK0955 # 02 Y:2016 02 2016 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $5,478 $10,800 Implemented
OK0955 # 06 Y:2016 06 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,112 $1,100 Implemented
OK0955 # 07 Y:2016 07 2016 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $580 $2,140 Implemented
OK0955 # 05 Y:2016 05 2016 RECOVER WASTE HEAT FROM EQUIPMENT $1,259 $5,448 Not Implemented
OK0955 # 01 Y:2016 01 2016 OPTIMIZE PLANT POWER FACTOR $6,635 $15,400 Not Implemented
OKO952 # 02 Y:2016 02 2016 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $29,900 $37,940 Not Implemented
OKO952 # 08 Y:2016 08 2016 INSTALL SET-BACK TIMERS $151 $160 Not Implemented
OKO952 # 07 Y:2016 07 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,312 $0 Implemented
OKO952 # 01 Y:2016 01 2016 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $39,072 $32,000 Implemented
OKO952 # 05 Y:2016 05 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,284 $6,222 Implemented
OKO952 # 04 Y:2016 04 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $11,021 $29,085 Implemented
OKO952 # 06 Y:2016 06 2016 OPTIMIZE PLANT POWER FACTOR $21,399 $82,500 Not Implemented
OKO952 # 03 Y:2016 03 2016 IMPROVE LUBRICATION PRACTICES $7,312 $0 Not Implemented
OK0949 # 02 Y:2016 02 2016 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $5,613 $3,847 Not Implemented
OK0949 # 04 Y:2016 04 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $720 $1,313 Not Implemented
OK0949 # 03 Y:2016 03 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,319 $5,020 Not Implemented
OK0949 # 08 Y:2016 08 2016 OPTIMIZE PLANT POWER FACTOR $11,423 $30,600 Not Implemented
OK0949 # 07 Y:2016 07 2016 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT $74,759 $284,084 Not Implemented
OK0949 # 01 Y:2016 01 2016 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $17,826 $50,400 Not Implemented
OK0949 # 05 Y:2016 05 2016 OPERATE BOILERS ON HIGH FIRE SETTING $10,228 $44,000 Not Implemented
OK0949 # 06 Y:2016 06 2016 COVER OPEN TANKS $9,702 $850 Not Implemented