Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
53
matching recommendationsSIC | 209 | Misc. Food And Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0281 # 01 Y:1996 | 01 | 1996 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $95,600 | $1,500 | Implemented |
AM0281 # 02 Y:1996 | 02 | 1996 | OPTIMIZE PLANT POWER FACTOR | $14,320 | $14,320 | Not Implemented |
AM0281 # 03 Y:1996 | 03 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $150 | $180 | Not Implemented |
AM0281 # 04 Y:1996 | 04 | 1996 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,250 | $2,370 | Implemented |
AM0281 # 05 Y:1996 | 05 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $950 | $470 | Implemented |
AM0281 # 06 Y:1996 | 06 | 1996 | PAY UTILITY BILLS ON TIME | $903 | $0 | Implemented |
AM0281 # 07 Y:1996 | 07 | 1996 | COMBINE UTILITY METERS | $245 | $0 | Implemented |
KG0061 # 03 Y:1996 | 03 | 1996 | INSTALL TIMERS AND/OR THERMOSTATS | $3,547 | $450 | Implemented |
KG0061 # 11 Y:1996 | 11 | 1996 | RECOVER AND REUSE COOLING WATER | $4,772 | $100 | Implemented |
KG0061 # 10 Y:1996 | 10 | 1996 | TREAT AND REUSE RINSE WATERS | $2,220 | $975 | Implemented |
KG0061 # 06 Y:1996 | 06 | 1996 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,004 | $40 | Implemented |
KG0061 # 05 Y:1996 | 05 | 1996 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,622 | $270 | Implemented |
KG0061 # 07 Y:1996 | 07 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,124 | $520 | Not Implemented |
KG0061 # 02 Y:1996 | 02 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $13,385 | $26,920 | Implemented |
KG0061 # 01 Y:1996 | 01 | 1996 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $55,998 | $50 | Implemented |
KG0061 # 04 Y:1996 | 04 | 1996 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $988 | $3,270 | Not Implemented |
KG0061 # 08 Y:1996 | 08 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,057 | $3,503 | Implemented |
KG0061 # 09 Y:1996 | 09 | 1996 | RECOVER AND REUSE COOLING WATER | $49,625 | $65,000 | Implemented |
AM0275 # 01 Y:1996 | 01 | 1996 | OPTIMIZE PLANT POWER FACTOR | $19,150 | $10,000 | Implemented |
AM0275 # 06 Y:1996 | 06 | 1996 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $190 | $0 | Implemented |
AM0275 # 05 Y:1996 | 05 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $450 | $60 | Implemented |
AM0275 # 04 Y:1996 | 04 | 1996 | PAY UTILITY BILLS ON TIME | $1,073 | $0 | Implemented |
AM0275 # 03 Y:1996 | 03 | 1996 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,820 | $0 | Implemented |
AM0275 # 02 Y:1996 | 02 | 1996 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $3,510 | $0 | Implemented |
KG0055 # 03 Y:1996 | 03 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,832 | $3,600 | Not Implemented |