Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
96
matching recommendationsSIC | 35 | Industrial Machinery And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0227 # 06 Y:2023 | 06 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,776 | $3,465 | n/a |
UU0227 # 03 Y:2023 | 03 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,325 | $78,840 | n/a |
UU0227 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,169 | $10,776 | n/a |
UU0227 # 07 Y:2023 | 07 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,564 | $7,061 | n/a |
UU0227 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,358 | $13,337 | n/a |
UU0227 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,103 | $7,349 | n/a |
UU0227 # 01 Y:2023 | 01 | 2023 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $14,399 | $40,790 | n/a |
UU0227 # 11 Y:2023 | 11 | 2023 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $2,160 | $2,000 | n/a |
UU0227 # 12 Y:2023 | 12 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $53 | $333 | n/a |
UU0227 # 09 Y:2023 | 09 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,237 | $6,000 | n/a |
UU0227 # 10 Y:2023 | 10 | 2023 | MINIMIZE WATER USAGE | $2,457 | $2,652 | n/a |
UU0227 # 08 Y:2023 | 08 | 2023 | INSTALL OCCUPANCY SENSORS | $4,289 | $9,282 | n/a |
UU0220 # 01 Y:2023 | 01 | 2023 | USE HEAT PUMP FOR SPACE CONDITIONING | $67,069 | $0 | Implemented |
UU0220 # 02 Y:2023 | 02 | 2023 | OPTIMIZE PLANT POWER FACTOR | $3,986 | $13,500 | Implemented |
UU0220 # 06 Y:2023 | 06 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $920 | $1,200 | Implemented |
UU0220 # 05 Y:2023 | 05 | 2023 | REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY | $1,160 | $50 | Implemented |
UU0220 # 04 Y:2023 | 04 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,245 | $3,810 | Not Implemented |
UU0220 # 03 Y:2023 | 03 | 2023 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $2,450 | $3,366 | Not Implemented |
UU0208 # 02 Y:2022 | 02 | 2022 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $6,476 | $127,045 | Implemented |
UU0208 # 05 Y:2022 | 05 | 2022 | INSTALL SKYLIGHTS | $3,058 | $10,560 | Not Implemented |
UU0208 # 04 Y:2022 | 04 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,292 | $7,290 | Implemented |
UU0208 # 03 Y:2022 | 03 | 2022 | OPTIMIZE PLANT POWER FACTOR | $4,445 | $12,840 | Implemented |
UU0208 # 01 Y:2022 | 01 | 2022 | USE POWER DURING OFF-PEAK PERIODS | $9,375 | $9,500 | Not Implemented |
UU0208 # 06 Y:2022 | 06 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $230 | $107 | Implemented |
UU0138 # 05 Y:2018 | 05 | 2018 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $615 | $0 | Implemented |