Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
14
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0125 # 01 Y:1991 | 01 | 1991 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $18,739 | $0 | Implemented |
OR0125 # 02 Y:1991 | 02 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,392 | $6,072 | Implemented |
OR0125 # 03 Y:1991 | 03 | 1991 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $12,391 | $35,042 | Implemented |
OR0125 # 04 Y:1991 | 04 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,743 | $0 | Implemented |
OR0125 # 05 Y:1991 | 05 | 1991 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $20,934 | $83,040 | Implemented |
OR0123 # 01 Y:1991 | 01 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,687 | $4,200 | Implemented |
OR0123 # 02 Y:1991 | 02 | 1991 | OPTIMIZE PLANT POWER FACTOR | $3,011 | $4,800 | Implemented |
OR0123 # 03 Y:1991 | 03 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,873 | $0 | Implemented |
OR0123 # 04 Y:1991 | 04 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $181 | $691 | Implemented |
OR0123 # 05 Y:1991 | 05 | 1991 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $16,124 | $0 | Implemented |
OR0109 # 01 Y:1991 | 01 | 1991 | INSULATE BARE EQUIPMENT | $1,432 | $1,506 | Not Implemented |
OR0109 # 02 Y:1991 | 02 | 1991 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $1,381 | $1,831 | Not Implemented |
OR0109 # 03 Y:1991 | 03 | 1991 | OPTIMIZE PLANT POWER FACTOR | $2,806 | $3,900 | Not Implemented |
OR0109 # 04 Y:1991 | 04 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $165 | $331 | Not Implemented |