Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
206
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0110 # 10 Y:2005 | 10 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $473 | $3,388 | Implemented |
IC0110 # 09 Y:2005 | 09 | 2005 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $17,156 | $81,881 | Implemented |
IC0110 # 08 Y:2005 | 08 | 2005 | OPTIMIZE PLANT POWER FACTOR | $13,904 | $70,000 | Implemented |
IC0110 # 07 Y:2005 | 07 | 2005 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $7,443 | $15,000 | Not Implemented |
IC0110 # 06 Y:2005 | 06 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,956 | $0 | Implemented |
IC0110 # 05 Y:2005 | 05 | 2005 | IMPROVE COMBUSTION CONTROL CAPABILITY | $13,789 | $3,500 | Implemented |
IC0110 # 01 Y:2005 | 01 | 2005 | REPLACE PURCHASED STEAM WITH OTHER ENERGY SOURCE | $106,617 | $213,420 | Implemented |
IC0110 # 02 Y:2005 | 02 | 2005 | SUBSTITUTE HOT PROCESS FLUIDS FOR STEAM | $79,621 | $634,572 | Not Implemented |
IC0110 # 03 Y:2005 | 03 | 2005 | REPAIR OR REPLACE STEAM TRAPS | $29,831 | $1,638 | Implemented |
IC0110 # 04 Y:2005 | 04 | 2005 | REPAIR AND ELIMINATE STEAM LEAKS | $6,051 | $400 | Implemented |
WI0503 # 07 Y:2005 | 07 | 2005 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,742 | $4,900 | Not Implemented |
WI0503 # 05 Y:2005 | 05 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,506 | $0 | Not Implemented |
WI0503 # 06 Y:2005 | 06 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,350 | $640 | Not Implemented |
WI0503 # 01 Y:2005 | 01 | 2005 | IMPROVE SPACE COMFORT CONDITIONING | $47,772 | $9,625 | Not Implemented |
WI0503 # 04 Y:2005 | 04 | 2005 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,112 | $1,000 | Not Implemented |
WI0503 # 03 Y:2005 | 03 | 2005 | USE OPTIMUM THICKNESS INSULATION | $8,005 | $7,500 | Not Implemented |
WI0503 # 02 Y:2005 | 02 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,209 | $21,960 | Not Implemented |
WI0502 # 02 Y:2005 | 02 | 2005 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $4,177 | $9,500 | Not Implemented |
WI0502 # 09 Y:2005 | 09 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,524 | $1,280 | Not Implemented |
WI0502 # 06 Y:2005 | 06 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,919 | $0 | Not Implemented |
WI0502 # 03 Y:2005 | 03 | 2005 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $3,880 | $0 | Not Implemented |
WI0502 # 07 Y:2005 | 07 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,670 | $520 | Not Implemented |
WI0502 # 01 Y:2005 | 01 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,862 | $27,000 | Not Implemented |
WI0502 # 05 Y:2005 | 05 | 2005 | INSTALL TIMERS AND/OR THERMOSTATS | $2,699 | $0 | Not Implemented |
WI0502 # 04 Y:2005 | 04 | 2005 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $3,880 | $0 | Not Implemented |