Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
39
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0304 # 09 Y:2004 | 09 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,328 | $271 | Not Implemented |
WV0304 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,051 | $210 | Implemented |
WV0304 # 03 Y:2004 | 03 | 2004 | DEVELOP A REPAIR/REPLACE POLICY | $11,373 | $220 | Not Implemented |
WV0304 # 02 Y:2004 | 02 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,964 | $2,752 | Implemented |
WV0304 # 10 Y:2004 | 10 | 2004 | INSULATE BARE EQUIPMENT | $509 | $44 | Implemented |
WV0304 # 01 Y:2004 | 01 | 2004 | BURN A LESS EXPENSIVE GRADE OF FUEL | $83,144 | $1,360 | Not Implemented |
WV0304 # 06 Y:2004 | 06 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,679 | $22 | Implemented |
WV0304 # 04 Y:2004 | 04 | 2004 | INSULATE BARE EQUIPMENT | $5,483 | $4,491 | Implemented |
WV0304 # 08 Y:2004 | 08 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,376 | $0 | Implemented |
WV0304 # 11 Y:2004 | 11 | 2004 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $418 | $154 | Implemented |
WV0304 # 07 Y:2004 | 07 | 2004 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $1,535 | $44 | Not Implemented |
WV0303 # 06 Y:2004 | 06 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,414 | $618 | Implemented |
WV0303 # 12 Y:2004 | 12 | 2004 | INSTALL OCCUPANCY SENSORS | $606 | $2,422 | Not Implemented |
WV0303 # 07 Y:2004 | 07 | 2004 | USE SYNTHETIC LUBRICANT | $1,981 | $560 | Implemented |
WV0303 # 08 Y:2004 | 08 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,770 | $236 | Implemented |
WV0303 # 09 Y:2004 | 09 | 2004 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $1,586 | $2,606 | Not Implemented |
WV0303 # 10 Y:2004 | 10 | 2004 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,061 | $414 | Implemented |
WV0303 # 11 Y:2004 | 11 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $816 | $515 | Implemented |
WV0303 # 05 Y:2004 | 05 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,576 | $8,537 | Implemented |
WV0303 # 04 Y:2004 | 04 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,262 | $137 | Not Implemented |
WV0303 # 03 Y:2004 | 03 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $6,999 | $3,622 | Not Implemented |
WV0303 # 02 Y:2004 | 02 | 2004 | DEVELOP A REPAIR/REPLACE POLICY | $8,151 | $458 | Implemented |
WV0303 # 01 Y:2004 | 01 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,432 | $0 | Not Implemented |
WV0303 # 13 Y:2004 | 13 | 2004 | INSULATE BARE EQUIPMENT | $171 | $303 | Implemented |
WV0303 # 14 Y:2004 | 14 | 2004 | RECOVER AND REUSE WASTE MATERIAL | $24,000 | $458 | Not Implemented |