Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
970
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0304 # 03 Y:2004 | 03 | 2004 | DEVELOP A REPAIR/REPLACE POLICY | $11,373 | $220 | Not Implemented |
WV0304 # 10 Y:2004 | 10 | 2004 | INSULATE BARE EQUIPMENT | $509 | $44 | Implemented |
WV0304 # 01 Y:2004 | 01 | 2004 | BURN A LESS EXPENSIVE GRADE OF FUEL | $83,144 | $1,360 | Not Implemented |
WV0304 # 02 Y:2004 | 02 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,964 | $2,752 | Implemented |
WV0304 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,051 | $210 | Implemented |
WV0304 # 04 Y:2004 | 04 | 2004 | INSULATE BARE EQUIPMENT | $5,483 | $4,491 | Implemented |
WV0304 # 08 Y:2004 | 08 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,376 | $0 | Implemented |
WV0304 # 06 Y:2004 | 06 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,679 | $22 | Implemented |
WV0304 # 09 Y:2004 | 09 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,328 | $271 | Not Implemented |
WV0304 # 07 Y:2004 | 07 | 2004 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $1,535 | $44 | Not Implemented |
WV0304 # 11 Y:2004 | 11 | 2004 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $418 | $154 | Implemented |
WV0303 # 13 Y:2004 | 13 | 2004 | INSULATE BARE EQUIPMENT | $171 | $303 | Implemented |
WV0303 # 01 Y:2004 | 01 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,432 | $0 | Not Implemented |
WV0303 # 02 Y:2004 | 02 | 2004 | DEVELOP A REPAIR/REPLACE POLICY | $8,151 | $458 | Implemented |
WV0303 # 03 Y:2004 | 03 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $6,999 | $3,622 | Not Implemented |
WV0303 # 10 Y:2004 | 10 | 2004 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,061 | $414 | Implemented |
WV0303 # 06 Y:2004 | 06 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,414 | $618 | Implemented |
WV0303 # 05 Y:2004 | 05 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,576 | $8,537 | Implemented |
WV0303 # 14 Y:2004 | 14 | 2004 | RECOVER AND REUSE WASTE MATERIAL | $24,000 | $458 | Not Implemented |
WV0303 # 11 Y:2004 | 11 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $816 | $515 | Implemented |
WV0303 # 07 Y:2004 | 07 | 2004 | USE SYNTHETIC LUBRICANT | $1,981 | $560 | Implemented |
WV0303 # 09 Y:2004 | 09 | 2004 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $1,586 | $2,606 | Not Implemented |
WV0303 # 08 Y:2004 | 08 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,770 | $236 | Implemented |
WV0303 # 04 Y:2004 | 04 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,262 | $137 | Not Implemented |
WV0303 # 12 Y:2004 | 12 | 2004 | INSTALL OCCUPANCY SENSORS | $606 | $2,422 | Not Implemented |