Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,002
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0418 # 06 Y:2012 | 06 | 2012 | USE PHOTOCELL CONTROLS | $18,400 | $14,100 | Implemented |
BD0418 # 04 Y:2012 | 04 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $26,689 | $30,000 | Not Implemented |
BD0418 # 08 Y:2012 | 08 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,441 | $600 | Implemented |
BD0418 # 13 Y:2012 | 13 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,210 | $1,500 | Implemented |
IP0006 # 03 Y:2012 | 03 | 2012 | INSTALL OCCUPANCY SENSORS | $1,771 | $730 | Implemented |
AM0627 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,546 | $980 | Implemented |
BD0418 # 02 Y:2012 | 02 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $64,077 | $313,924 | Implemented |
AM0627 # 05 Y:2012 | 05 | 2012 | INSTALL OCCUPANCY SENSORS | $609 | $2,640 | Not Implemented |
AM0627 # 03 Y:2012 | 03 | 2012 | USE SYNTHETIC LUBRICANT | $2,906 | $0 | Not Implemented |
BD0418 # 07 Y:2012 | 07 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,842 | $6,000 | Not Implemented |
BD0418 # 09 Y:2012 | 09 | 2012 | INSTALL SKYLIGHTS | $5,048 | $12,215 | Implemented |
AM0627 # 04 Y:2012 | 04 | 2012 | USE PHOTOCELL CONTROLS | $1,384 | $520 | Not Implemented |
BD0418 # 14 Y:2012 | 14 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,121 | $1,225 | Implemented |
BD0418 # 05 Y:2012 | 05 | 2012 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $23,015 | $48,000 | Not Implemented |
BD0418 # 15 Y:2012 | 15 | 2012 | MOVE PRODUCT USING MECHANICAL MEANS | $12,870 | $20,000 | Implemented |
BD0418 # 03 Y:2012 | 03 | 2012 | USE RADIANT HEATER FOR SPOT HEATING | $60,134 | $105,100 | Not Implemented |
BD0418 # 10 Y:2012 | 10 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,117 | $20 | Implemented |
IP0006 # 02 Y:2012 | 02 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $980 | $0 | Implemented |
BD0418 # 11 Y:2012 | 11 | 2012 | INSTALL OCCUPANCY SENSORS | $2,653 | $1,200 | Implemented |
AM0627 # 01 Y:2012 | 01 | 2012 | UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS | $66,393 | $99,038 | Not Implemented |
IP0006 # 01 Y:2012 | 01 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,520 | $0 | Implemented |
IP0006 # 04 Y:2012 | 04 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,847 | $1,416 | Not Implemented |
BD0418 # 01 Y:2012 | 01 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $147,427 | $200,000 | Implemented |
BD0418 # 12 Y:2012 | 12 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,527 | $500 | Implemented |
IP0006 # 05 Y:2012 | 05 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $490 | $1,156 | Not Implemented |